[2017] KEHC 3089 (KLR)

[2017] KEHC 3089 (KLR)

The court found that although the written JBC Agreement was not executed by both parties, an oral contract existed, and the parties' conduct demonstrated adoption of the standard terms. The Plaintiff performed its obligations by undertaking construction works and submitting interim claims, which the Defendant...

Source-derived case information.

Citation
[2017] KEHC 3089 (KLR)
Parties
Plaintiff: Trishcon Construction Co. Ltd; Defendant: Avtar Singh Bahra
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 152 of 2015
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff's claim allowed in part; Defendant's counterclaim dismissed.
Legal Topics
Breach of Contract, Construction Disputes, Quantum Meruit, Damages Assessment
Source Language
english
Commercial and Corporate Civil Procedure Breach of Contract Construction Disputes Quantum Meruit Damages Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Trishcon Construction Co. Ltd

Plaintiff

Avtar Singh Bahra

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Was there a valid building contract between the Plaintiff and the Defendant, and what were its terms?
  2. 2 Did either party breach the contract, and if so, what was the nature of the breach?
  3. 3 Is the Plaintiff entitled to payment for works done and damages for alleged unlawful retention of equipment?

Ratio Decidendi

The court found that although the written JBC Agreement was not executed by both parties, an oral contract existed, and the parties' conduct demonstrated adoption of the standard terms. The Plaintiff performed its obligations by undertaking construction works and submitting interim claims, which the Defendant partially paid without contesting the amounts or raising timely objections. The Defendant's unilateral underpayment and failure to pay the final account constituted breach of contract. The Defendant failed to prove any substantial defects or poor workmanship by the Plaintiff, nor did he provide sufficient evidence for his counterclaim of loss of rental income or additional completion...

Court Disposition

Plaintiff's claim allowed in part; Defendant's counterclaim dismissed.

Orders

  • Plaintiff awarded Kshs. 6,752,810 as compensation for unpaid works.
  • Defendant to allow Plaintiff free access to collect its equipment and machinery or salvage thereof.