https://new.kenyalaw.org/akn/ke/judgment/kehc/2026/8649

https://new.kenyalaw.org/akn/ke/judgment/kehc/2026/8649

The Applicant did not demonstrate any request to the Respondent to agree on or appoint an arbitrator, any notice of default under section 12(3) of the Arbitration Act, or expiry of the statutory 14-day period. The Applicant instead approached the Chartered Institute of Arbitrators directly, which was not the...

Source-derived case information.

Citation
[2026] KEHC 8649 (KLR)
Parties
Applicant: Tristar Heights Management Limited; Respondent: Bridge The Gap Limited
Court
High Court
Jurisdiction
Kenya
Case Number
Miscellaneous Application E1163 of 2025
Procedural Posture
Miscellaneous Application / Ruling on Application for Appointment of Arbitrator / Vesting Order
Outcome
Application struck out with costs
Judges
["JWW Mong'are"]
Legal Topics
Appointment of Arbitrator, Section 12 Arbitration Act, Court Intervention in Arbitral Appointment, Prematurity of Application, Contractual Arbitration Clause
Source Language
en
Arbitration Commercial Law Appointment of Arbitrator Section 12 Arbitration Act Court Intervention in Arbitral Appointment Prematurity of Application Contractual Arbitration Clause

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Tristar Heights Management Limited

Applicant

Bridge The Gap Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application for Appointment of Arbitrator / Vesting Order

  1. 1 Whether the court should appoint a sole arbitrator under section 12 of the Arbitration Act
  2. 2 Whether the Applicant complied with the statutory procedure before seeking court intervention
  3. 3 Whether any stalemate or refusal by the Respondent to agree on an arbitrator was proved

Ratio Decidendi

The Applicant did not demonstrate any request to the Respondent to agree on or appoint an arbitrator, any notice of default under section 12(3) of the Arbitration Act, or expiry of the statutory 14-day period. The Applicant instead approached the Chartered Institute of Arbitrators directly, which was not the contractual appointing process. The application was therefore premature and the court had no basis to intervene under section 12.

Court Disposition

Application struck out with costs

Orders

  • The Notice of Motion dated 19th November 2025 is struck out.
  • Costs awarded to the Respondent.