[2018] KEHC 4435 (KLR)

[2018] KEHC 4435 (KLR)

The court found that the ongoing disputes between the shareholders had paralyzed the operations of Eldama Ravine Stones Limited, resulting in the company failing to fulfill its statutory obligations and risking further legal and financial peril. Both parties' proposals were considered, but the court determined that...

Source-derived case information.

Citation
[2018] KEHC 4435 (KLR)
Parties
Plaintiff: Udali Group Limited; Defendant: Umberto Rtccardo Dellavale; Defendant: Fiesquis Marina Mariam Cisse Mboisseme; Defendant: Deci Group Limited; Defendant: Eldama Ravine Stones Limited
Court
High Court
Court Station
High Court at Meru
Jurisdiction
Kenya
Case Number
Civil Suit 12 of 2017
Procedural Posture
Civil Suit / Interlocutory Ruling on Management of Company Assets Pending Suit Determination
Outcome
General meeting ordered for appointment of independent directors to manage company pending suit; detailed operational directions issued.
Judges
F Gikonyo
Legal Topics
Company Management Disputes, Appointment of Directors, Shareholder Rights, Interlocutory Orders
Source Language
en
Commercial and Corporate Civil Procedure Company Management Disputes Appointment of Directors Shareholder Rights Interlocutory Orders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Udali Group Limited

Plaintiff

Umberto Rtccardo Dellavale

Defendant

Fiesquis Marina Mariam Cisse Mboisseme

Defendant

Deci Group Limited

Defendant

Eldama Ravine Stones Limited

Defendant

Procedural Posture

Civil Suit / Interlocutory Ruling on Management of Company Assets Pending Suit Determination

  1. 1 Whether the court should intervene in the management of Eldama Ravine Stones Limited pending resolution of the dispute.
  2. 2 Whether the plaintiff should be granted control of the company assets and operations.
  3. 3 What mechanism should be put in place to protect the interests of both shareholders and the company during the pendency of the suit.

Ratio Decidendi

The court found that the ongoing disputes between the shareholders had paralyzed the operations of Eldama Ravine Stones Limited, resulting in the company failing to fulfill its statutory obligations and risking further legal and financial peril. Both parties' proposals were considered, but the court determined that neither party should have unilateral control over the company or its assets while the suit was pending. Instead, the court exercised its statutory power to order the convening of a general meeting for the appointment of independent directors, who would be responsible for managing the company and its assets in a manner that protects the interests of all shareholders. The court...

Court Disposition

General meeting ordered for appointment of independent directors to manage company pending suit; detailed operational directions issued.

Orders

  • A general meeting of Eldama Ravine Stones Limited to be convened on 7th June 2018 at the registered office for the purpose of appointing two or more suitable directors.
  • Each party to nominate one person (not a current director or closely associated with the shareholder companies) to be appointed as director; a third director to be agreed upon or nominated for court determination if no agreement.