[2004] KEHC 1672 (KLR)

[2004] KEHC 1672 (KLR)

The court found that the arbitrator did not exceed his terms of reference and properly applied the contract and the law. The applicant had possession of the site as at the date of signing the contract, and the subsequent inability to proceed due to landowner disputes and court injunctions did not constitute a...

Source-derived case information.

Citation
[2004] KEHC 1672 (KLR)
Parties
Applicant: Unispan Limited; Respondent: The Project Manager, El Nino Emergency Project
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Children Miscellaneous Application 250 of 2004
Procedural Posture
Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award
Outcome
application dismissed with costs to the respondent
Legal Topics
Arbitration Award Challenge, Setting Aside Award, Contractual Liability, Liquidated Damages, Vat Refund, Extended Costs
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Award Challenge Setting Aside Award Contractual Liability Liquidated Damages Vat Refund Extended Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Unispan Limited

Applicant

The Project Manager, El Nino Emergency Project

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award

  1. 1 Whether the arbitrator exceeded his terms of reference under the contract and Arbitration Act.
  2. 2 Whether the failure to grant access to part of the site constituted a compensation event under the contract.
  3. 3 Whether the applicant is liable to pay liquidated damages for the specified period.

Ratio Decidendi

The court found that the arbitrator did not exceed his terms of reference and properly applied the contract and the law. The applicant had possession of the site as at the date of signing the contract, and the subsequent inability to proceed due to landowner disputes and court injunctions did not constitute a compensation event under Clause 44.1(a). The arbitrator's finding on liquidated damages was upheld as the applicant failed to provide sufficient evidence to challenge the award. Regarding VAT refund, the contract placed responsibility on the contractor, and changes in the law rendered the employer's involvement inapplicable. The applicant's claims for extended costs were unsupported...

Court Disposition

application dismissed with costs to the respondent

Orders

  • The application dated 14th April 2004 to set aside the arbitral award is dismissed.
  • Costs of the application are awarded to the respondent.