[2009] KECA 423 (KLR)

[2009] KECA 423 (KLR)

The Court of Appeal held that the disputes raised by the appellant—including claims that the amounts certified by the architect exceeded the contractual sums and that interest was being claimed at a rate not provided for in the contracts—constituted disputes or differences within the meaning of the arbitration...

Source-derived case information.

Citation
[2009] KECA 423 (KLR)
Parties
Appellant: University of Nairobi; Respondent: N.K. Brothers Limited
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 309 of 2002
Procedural Posture
Civil Appeal / Appeal From High Court Ruling on Stay of Proceedings and Referral to Arbitration
Outcome
appeal allowed; High Court order set aside; suit referred to arbitration
Legal Topics
Arbitration Clauses, Building Contracts, Contractual Disputes, Final Certificates, Interest on Awards
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Clauses Building Contracts Contractual Disputes Final Certificates Interest on Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

University of Nairobi

Appellant

N.K. Brothers Limited

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Ruling on Stay of Proceedings and Referral to Arbitration

  1. 1 Whether the dispute between the parties, as pleaded, falls within the scope of the arbitration clause in the contracts and should be referred to arbitration.
  2. 2 Whether the issuance of architect's certificates precludes the employer from disputing the amounts claimed by the contractor.
  3. 3 Whether the claim for interest at 32% per annum is covered by the contract or constitutes a separate dispute.

Ratio Decidendi

The Court of Appeal held that the disputes raised by the appellant—including claims that the amounts certified by the architect exceeded the contractual sums and that interest was being claimed at a rate not provided for in the contracts—constituted disputes or differences within the meaning of the arbitration clause (clause 36) in the contracts. The Court found that the arbitration clause was broadly worded to cover any dispute or difference arising out of or in connection with the contracts, including disputes over the amounts certified by the architect. The Court rejected the respondent's argument that the employer was bound by the architect's certificates regardless of their content,...

Court Disposition

appeal allowed; High Court order set aside; suit referred to arbitration

Orders

  • The appeal is allowed.
  • The order of the superior court made on 23rd July, 2001 is set aside.