[2020] KEHC 9802 (KLR)

[2020] KEHC 9802 (KLR)

The court held that the consent order entered into by the parties on 18th July 2019 was a binding contractual agreement intended to settle the plaintiff's indebtedness to the Bank and bring the dispute to an end. The plaintiff failed to comply with the terms of the consent order, including timely payment and...

Source-derived case information.

Citation
[2020] KEHC 9802 (KLR)
Parties
Plaintiff: Upways Investments Limited; Defendant: HF Group (Formerly Housing Finance Company of Kenya Ltd); Defendant: Muga Auctioneers & General Merchants; Defendant: Taifa Auctioneers
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 229 of 2017
Procedural Posture
Civil Case / Ruling on Interlocutory Application to Extend Time for Compliance With Consent Order and for Injunction
Outcome
application dismissed with costs to the 1st defendant
Judges
DAS Majanja
Legal Topics
Consent Judgments, Loan Recovery, Injunctive Relief, Variation of Orders
Source Language
en
Commercial and Corporate Civil Procedure Consent Judgments Loan Recovery Injunctive Relief Variation of Orders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 8 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Upways Investments Limited

Plaintiff

HF Group (Formerly Housing Finance Company of Kenya Ltd)

Defendant

Muga Auctioneers & General Merchants

Defendant

Taifa Auctioneers

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Application to Extend Time for Compliance With Consent Order and for Injunction

  1. 1 Whether the court can extend time for the plaintiff to comply with the consent order dated 18th July 2019.
  2. 2 Whether the plaintiff has established grounds for variation or setting aside of the consent order.
  3. 3 Whether the plaintiff is entitled to an interlocutory injunction restraining the defendants from dealing with the suit properties.

Ratio Decidendi

The court held that the consent order entered into by the parties on 18th July 2019 was a binding contractual agreement intended to settle the plaintiff's indebtedness to the Bank and bring the dispute to an end. The plaintiff failed to comply with the terms of the consent order, including timely payment and provision of an acceptable bank undertaking. The court found that the plaintiff had not alleged or established any grounds such as fraud, misrepresentation, or mistake that would justify varying or setting aside the consent order. The court emphasized that it cannot force the Bank to accept proposals outside the terms of the consent order and that the Bank was entitled to exercise its...

Court Disposition

application dismissed with costs to the 1st defendant

Orders

  • The Notice of Motion dated 22nd April 2020 is dismissed with costs to the 1st defendant.