[2021] KEELC 2944 (KLR)

[2021] KEELC 2944 (KLR)

The court found that the sale agreement expressly provided for a completion date of 90 days from the date of the agreement, which was 14th February, 2019. The plaintiff's argument that the completion period should run from the date it received the executed counterpart was unsupported by the contract's terms. The...

Source-derived case information.

Citation
[2021] KEELC 2944 (KLR)
Parties
Plaintiff: Urithi Housing Co-operative Society Ltd; Defendant: Ndima Tea Factory Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 208 of 2019
Procedural Posture
Injunction Application / Ruling on Interlocutory Application
Outcome
application dismissed
Legal Topics
Sale of Land, Specific Performance, Temporary Injunctions, Contractual Completion Dates
Source Language
en
Land and Property Civil Procedure Sale of Land Specific Performance Temporary Injunctions Contractual Completion Dates

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Urithi Housing Co-operative Society Ltd

Plaintiff

Ndima Tea Factory Limited

Defendant

Procedural Posture

Injunction Application / Ruling on Interlocutory Application

  1. 1 Whether the plaintiff is entitled to a temporary injunction restraining the defendant from rescinding or interfering with the sale agreement for the suit properties.
  2. 2 Whether the completion and rescission notices served by the defendant were premature, invalid, null and void.
  3. 3 Whether the plaintiff established a prima facie case with a probability of success to warrant the grant of a temporary injunction.

Ratio Decidendi

The court found that the sale agreement expressly provided for a completion date of 90 days from the date of the agreement, which was 14th February, 2019. The plaintiff's argument that the completion period should run from the date it received the executed counterpart was unsupported by the contract's terms. The defendant acted within its contractual rights by issuing completion and rescission notices after the plaintiff failed to complete the transaction within the stipulated period. The agreement allowed for extension of the completion date solely at the defendant's discretion, and the defendant was under no obligation to grant such extension. The plaintiff failed to establish a prima...

Court Disposition

application dismissed

Orders

  • The plaintiff's application dated 20th June, 2019 is dismissed with costs to the defendant.
  • The interim orders granted on 4th July, 2019 and extended on 2nd December, 2019, 3rd June, 2020 and 12th November, 2020 are discharged.