[2025] KEELC 2848 (KLR)

[2025] KEELC 2848 (KLR)

The court found that the Plaintiffs and Defendant entered into a valid easement agreement in 1993, granting the Defendant the right to lay pipelines within a 30-meter width for 99 years in exchange for compensation of Kshs. 494,240/-, which the Plaintiffs acknowledged receiving. The agreement did not limit the...

Source-derived case information.

Citation
[2025] KEELC 2848 (KLR)
Parties
Plaintiff: Nizar Hasham Virani; Plaintiff: Shamsudin Gulamhussein Nanji; Defendant: Kenya Pipeline Company Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Kisumu
Jurisdiction
Kenya
Case Number
Environment and Land Case Civil Suit 357 of 2015
Procedural Posture
Civil Suit / Judgment
Outcome
suit dismissed with costs to the defendant
Judges
SO Okong'o
Legal Topics
Easements, Compensation for Land Use, Trespass, Special Damages, Pleadings, Burden of Proof
Source Language
en
Land and Property Civil Procedure Easements Compensation for Land Use Trespass Special Damages Pleadings Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 12 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Nizar Hasham Virani

Plaintiff

Shamsudin Gulamhussein Nanji

Plaintiff

Kenya Pipeline Company Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Plaintiffs are entitled to compensation from the Defendant for the use of their land under the easement agreement.
  2. 2 Whether the Plaintiffs proved their claim for special damages for alleged losses and damage to the suit property.
  3. 3 Whether the Defendant's actions amounted to trespass or discrimination against the Plaintiffs.

Ratio Decidendi

The court found that the Plaintiffs and Defendant entered into a valid easement agreement in 1993, granting the Defendant the right to lay pipelines within a 30-meter width for 99 years in exchange for compensation of Kshs. 494,240/-, which the Plaintiffs acknowledged receiving. The agreement did not limit the number of pipelines, only the area, and the second pipeline was within the easement's scope. The Plaintiffs did not plead or prove that the easement agreement was null and void in their pleadings, and thus could not challenge its validity at the submission stage. The Plaintiffs' claim for special damages was not supported by specific evidence or proof as required by law. The court...

Court Disposition

suit dismissed with costs to the defendant

Orders

  • The Plaintiffs' suit is dismissed with costs to the Defendant.