[2024] KEHC 691 (KLR)

[2024] KEHC 691 (KLR)

The Court found that both the contract and Bill of Quantities were properly executed and binding, as evidenced by the signatures of both parties. Clause 29 of the contract entitled the Plaintiff to interest on delayed payments, and there was no express waiver of this right by the Plaintiff. The Defendant's argument...

Source-derived case information.

Citation
[2024] KEHC 691 (KLR)
Parties
Plaintiff: Vishva Builders Limited; Defendant: Moi University
Court
High Court
Court Station
High Court at Eldoret
Jurisdiction
Kenya
Case Number
Civil Case 51 of 1999
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the Plaintiff in full.
Judges
JRA Wananda
Legal Topics
Construction Contracts, Breach of Contract, Interest on Delayed Payments, Agency of Consultants, Arbitration Clauses, Loss and Expense Claims
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Breach of Contract Interest on Delayed Payments Agency of Consultants Arbitration Clauses Loss and Expense Claims

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Vishva Builders Limited

Plaintiff

Moi University

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the contract, including the Bill of Quantities, was properly executed and binding on the parties.
  2. 2 Whether the correct procedure was followed in issuing Interim Certificates No. 8-13 and if they were valid.
  3. 3 Whether the Departmental Representative (D.R.), Quantity Surveyor (QS), Clerk of Works and other consultants were agents of the Defendant whose acts bound the Defendant.

Ratio Decidendi

The Court found that both the contract and Bill of Quantities were properly executed and binding, as evidenced by the signatures of both parties. Clause 29 of the contract entitled the Plaintiff to interest on delayed payments, and there was no express waiver of this right by the Plaintiff. The Defendant's argument that the Plaintiff accepted a waiver was not supported by the correspondence or conduct of the parties. The D.R., QS, and Clerk of Works were agents of the Defendant, and their certification of sums due bound the Defendant. Certificates 8-13 were issued following the agreed procedure, and the Defendant's subsequent unilateral cancellation of these certificates was irregular,...

Court Disposition

Judgment for the Plaintiff in full.

Orders

  • The Defendant shall pay the Plaintiff Kshs 185,305,011.30.
  • Interest thereon at prevailing bank rates from the date of filing suit until payment in full.