The court found that the applicant had established a liquidated claim based on interim certificates issued under the construction contract, which included provision for interest on delayed payments as per the Bills of Quantities. The respondent's defence, including the purported cancellation of certificates and...

Source-derived case information.

Citation
[2002] KEHC 1143 (KLR)
Parties
Applicant: Vishva Builders Ltd; Respondent: Moi University
Court
High Court
Court Station
High Court at Eldoret
Jurisdiction
Kenya
Case Number
Civil Case 51 of 1999
Procedural Posture
Summary Judgment Application / Ruling on Application for Summary Judgment Under Order Xxxv Rules 1 and 2 of the Civil Procedure Rules
Outcome
summary judgment granted for the applicant as prayed in the motion, with costs to the applicant
Legal Topics
Summary Judgment, Construction Contracts, Liquidated Demands, Interim Certificates, Interest on Delayed Payments, Agency in Contracts
Source Language
en
Civil Procedure Commercial and Corporate Summary Judgment Construction Contracts Liquidated Demands Interim Certificates Interest on Delayed Payments Agency in Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Vishva Builders Ltd

Applicant

Moi University

Respondent

Procedural Posture

Summary Judgment Application / Ruling on Application for Summary Judgment Under Order Xxxv Rules 1 and 2 of the Civil Procedure Rules

  1. 1 Whether the applicant is entitled to summary judgment for a liquidated sum based on interim certificates issued under a construction contract.
  2. 2 Whether the respondent has demonstrated a bona fide triable issue to warrant leave to defend the suit.
  3. 3 Whether the inclusion of interest and additional expenses in the interim certificates was valid under the contract.

Ratio Decidendi

The court found that the applicant had established a liquidated claim based on interim certificates issued under the construction contract, which included provision for interest on delayed payments as per the Bills of Quantities. The respondent's defence, including the purported cancellation of certificates and reliance on pre-contract correspondence, was not bona fide. The DR acted as the respondent's agent, and any dispute over the validity of certificates was a matter between the respondent and its agent, not the applicant. The respondent failed to raise any dispute or refer the matter to arbitration within a reasonable time, and only challenged the certificates after the suit was...

Court Disposition

summary judgment granted for the applicant as prayed in the motion, with costs to the applicant

Orders

  • Summary judgment is entered for the applicant against the respondent as prayed in the plaint.
  • The respondent shall pay the costs of this application to the applicant.