[2023] KEHC 24542 (KLR)

[2023] KEHC 24542 (KLR)

The court found that the application for interim measures of protection was premature because the applicant had not complied with the contractual dispute resolution mechanism, specifically the requirement to refer disputes to a Dispute Adjudication Board (DAB) before proceeding to arbitration. The relevant clauses...

Source-derived case information.

Citation
[2023] KEHC 24542 (KLR)
Parties
Applicant: Vshydro Kenya Limited; Respondent: Settet Power Generation Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Case E054 of 2023
Procedural Posture
Chamber Summons Application / Ruling on Interim Measures of Protection Pending Arbitration
Outcome
application struck out as premature
Judges
MN Mwangi
Legal Topics
Arbitration Agreements, Interim Measures, Epc Contracts, Breach of Contract, Dispute Adjudication Board, Contractual Obligations
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreements Interim Measures Epc Contracts Breach of Contract Dispute Adjudication Board Contractual Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2
Sign in to unlock

Parties

Vshydro Kenya Limited

Applicant

Settet Power Generation Company Limited

Respondent

Procedural Posture

Chamber Summons Application / Ruling on Interim Measures of Protection Pending Arbitration

  1. 1 Whether the application for interim measures of protection is premature under the contract's dispute resolution clauses.
  2. 2 Whether the applicant is entitled to interim protection orders pending arbitration.
  3. 3 Whether the subject matter of the intended arbitration is under threat warranting court intervention.

Ratio Decidendi

The court found that the application for interim measures of protection was premature because the applicant had not complied with the contractual dispute resolution mechanism, specifically the requirement to refer disputes to a Dispute Adjudication Board (DAB) before proceeding to arbitration. The relevant clauses (20.2, 20.4, 20.6, and 20.8) of the EPC contracts require parties to attempt amicable settlement and, failing that, to refer disputes to a DAB. Only if there is no DAB in place or the DAB is unable to render a decision can the matter proceed directly to arbitration. The applicant did not notify the respondent of its intention to refer the dispute to a DAB or provide reasons for...

Court Disposition

application struck out as premature

Orders

  • The Chamber Summons application dated 16th February, 2023 is struck out with costs to the defendants.