The court found that the 2nd Respondent's project was correctly classified as medium risk under the amended Second Schedule of EMCA by Legal Notice No. 31 of 2019, which was in force at the time of the EIA application. Consequently, only Regulation 7 applied, not Regulation 17, and the requirements for public...

Source-derived case information.

Citation
[2025] KEELC 4756 (KLR)
Parties
Applicant: Ndirangu Wa Maina (Suing on His Own Behalf and as the Chairman of Lavington Five Roads Association); Respondent: National Environment Management Authority; Respondent: Woodridge Centre Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment and Land Appeal E007 of 2023
Procedural Posture
Environment and Land Appeal / Judgment
Outcome
appeal dismissed
Judges
AA Omollo
Legal Topics
Environmental Impact Assessment, Public Participation, Project Classification, Regulatory Compliance
Source Language
en
Environmental Law Administrative Law Environmental Impact Assessment Public Participation Project Classification Regulatory Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2
Sign in to unlock

Parties

Ndirangu Wa Maina (Suing on His Own Behalf and as the Chairman of Lavington Five Roads Association)

Applicant

National Environment Management Authority

Respondent

Woodridge Centre Limited

Respondent

Procedural Posture

Environment and Land Appeal / Judgment

  1. 1 Whether the 2nd Respondent's project was correctly classified as medium or high risk under the Environmental Management and Coordination Act and relevant legal notices.
  2. 2 Whether adequate public participation was undertaken prior to the issuance of the Environmental Impact Assessment (EIA) license.
  3. 3 Whether the EIA license granted to the 2nd Respondent is null and void due to alleged procedural and substantive defects.

Ratio Decidendi

The court found that the 2nd Respondent's project was correctly classified as medium risk under the amended Second Schedule of EMCA by Legal Notice No. 31 of 2019, which was in force at the time of the EIA application. Consequently, only Regulation 7 applied, not Regulation 17, and the requirements for public participation were less stringent. The court determined that public participation was undertaken through meetings and questionnaires, and that objections by the applicant and other stakeholders were considered, even if not all were accepted. The court emphasized that the effectiveness of public participation depends on the circumstances and that there is no single prescribed method....

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed for lack of merit.
  • Each party shall bear its own costs.