[2017] KEHC 5860 (KLR)

[2017] KEHC 5860 (KLR)

The court found that the dispute between the parties arose in October 2013 when West Mount terminated the contract and took over the construction site. Tridev's letter of 8 October 2013 to West Mount, which contested the termination and reserved the right to activate the dispute resolution provision, constituted...

Source-derived case information.

Citation
[2017] KEHC 5860 (KLR)
Parties
Applicant: West Mount Investments Limited; Respondent: Tridev Builders Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 230 of 2016
Procedural Posture
Miscellaneous Application / Judgment
Outcome
application dismissed
Legal Topics
Arbitration Agreements, Contractual Time Bars, Construction Contracts, Kompetenz Kompetenz, Notice of Dispute, Jurisdiction of Arbitral Tribunal
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreements Contractual Time Bars Construction Contracts Kompetenz Kompetenz Notice of Dispute Jurisdiction of Arbitral Tribunal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2
Sign in to unlock

Parties

West Mount Investments Limited

Applicant

Tridev Builders Company Limited

Respondent

Procedural Posture

Miscellaneous Application / Judgment

  1. 1 Whether the arbitrator had jurisdiction to determine the dispute between the parties under the JBC Agreement.
  2. 2 Whether Tridev Builders Company Limited complied with the contractual time-bar clause (Clause 45.3) by notifying West Mount Investments Limited of the dispute within ninety days of its occurrence.
  3. 3 Whether the arbitration was validly commenced in accordance with the arbitration agreement.

Ratio Decidendi

The court found that the dispute between the parties arose in October 2013 when West Mount terminated the contract and took over the construction site. Tridev's letter of 8 October 2013 to West Mount, which contested the termination and reserved the right to activate the dispute resolution provision, constituted sufficient notice of dispute within the ninety-day period required by Clause 45.3 of the JBC Agreement. The court held that the purpose of the time-bar clause was to ensure prompt notification and resolution of disputes, and that substantial compliance was achieved by Tridev's letter. The subsequent engagement between the parties in attempts to resolve the dispute amicably further...

Court Disposition

application dismissed

Orders

  • The Originating Summons dated 15th June 2016 is dismissed with costs to the Respondent.
  • The arbitrator as appointed has jurisdiction to consider and determine the dispute between the parties.