[2023] KEHC 24142 (KLR)

[2023] KEHC 24142 (KLR)

The court found that the plaintiff and defendant entered into a valid contract for construction works at Moi International Airport, with a contract sum of Ksh. 125,125,179.45. The plaintiff was paid Ksh. 110,508,588.20 for certified works. The plaintiff failed to complete all contracted works and did not obtain a...

Source-derived case information.

Citation
[2023] KEHC 24142 (KLR)
Parties
Plaintiff: Westcon Contractors Limited; Defendant: Kenya Airways Authority
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 3 of 2018
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's suit dismissed except for retention money; defendant to pay balance of retention after deducting costs.
Judges
DKN Magare
Legal Topics
Breach of Contract, Construction Contracts, Quantum Meruit, Contractual Variations, Retention Money, Pleadings and Proof
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Quantum Meruit Contractual Variations Retention Money Pleadings and Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 19 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Westcon Contractors Limited

Plaintiff

Kenya Airways Authority

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant breached the contract dated 4th February 2015 by failing to pay the plaintiff the claimed sums and retention money.
  2. 2 Whether the plaintiff is entitled to the claimed sums, including retention, under the contract or on a quantum meruit basis.
  3. 3 Whether the plaintiff performed its contractual obligations to completion as required by the contract terms.

Ratio Decidendi

The court found that the plaintiff and defendant entered into a valid contract for construction works at Moi International Airport, with a contract sum of Ksh. 125,125,179.45. The plaintiff was paid Ksh. 110,508,588.20 for certified works. The plaintiff failed to complete all contracted works and did not obtain a final certificate for the remaining works. The plaintiff's claim for additional sums beyond the contract amount was not supported by evidence of variation or proper certification, nor was quantum meruit pleaded. The court held that parties are bound by their contract and pleadings, and the plaintiff failed to strictly prove the sums claimed. The only sum contractually due was the...

Court Disposition

Plaintiff's suit dismissed except for retention money; defendant to pay balance of retention after deducting costs.

Orders

  • Plaintiff's suit dismissed in limine with costs of Ksh. 1,206,335 deducted from the retention amount.
  • Defendant to pay the balance of the retention amount, Ksh. 9,844,523.80, by 24/11/2023.