[2015] KEHC 4519 (KLR)

[2015] KEHC 4519 (KLR)

The court found that the Defendant's termination of the sub-contract was not justified under Article 9 of the contract, as the reasons given—primarily the Plaintiff's performance on a separate contract and instructions from KPLC—were extraneous to the Dagoretti contract and not valid grounds for termination. The...

Source-derived case information.

Citation
[2015] KEHC 4519 (KLR)
Parties
Plaintiff: WIL Developers & Construction Ltd.; Defendant: KEC International Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Judgment Date
29 May 2015
Case Number
Civil Suit 575 of 2014
Procedural Posture
Civil Suit / Ruling on Interlocutory Injunction Pending Arbitration
Outcome
Application for temporary injunction granted pending arbitration.
Judges
DO Ogembo
Legal Topics
Contract Termination, Injunctive Relief, Arbitration Clauses, Breach of Contract
Source Language
english
Commercial and Corporate Civil Procedure Contract Termination Injunctive Relief Arbitration Clauses Breach of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

WIL Developers & Construction Ltd.

Plaintiff

KEC International Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Injunction Pending Arbitration

  1. 1 Whether the termination of the sub-contract by the Defendant was justified under the contract terms.
  2. 2 Whether there is a valid sub-contract between the Defendant and a third party over the Dagoretti site.
  3. 3 Whether the Plaintiff is entitled to a temporary injunction pending arbitration.

Ratio Decidendi

The court found that the Defendant's termination of the sub-contract was not justified under Article 9 of the contract, as the reasons given—primarily the Plaintiff's performance on a separate contract and instructions from KPLC—were extraneous to the Dagoretti contract and not valid grounds for termination. The court rejected the Defendant's assertion that the Plaintiff consented to the termination, finding no evidence of such consent. The court also found insufficient proof that a new sub-contractor had lawfully taken over the Dagoretti site. Applying the principles for granting an injunction, the court held that the Plaintiff had established a prima facie case, that damages would not...

Court Disposition

Application for temporary injunction granted pending arbitration.

Orders

  • A temporary injunction is issued restraining the Defendant and its agents from interfering with and/or taking possession of the Dagoretti site until the dispute is determined by arbitration.
  • The costs of this application shall be in the cause.