[2021] KEHC 7225 (KLR)

[2021] KEHC 7225 (KLR)

The court found that the contract between the parties was validly varied by mutual agreement and conduct, despite the defendant's failure to formally execute the addendum. The plaintiff completed phases 1 to 4 in full and phase 5 to 90%, with joint inspections and certifications confirming satisfactory completion....

Source-derived case information.

Citation
[2021] KEHC 7225 (KLR)
Parties
Plaintiff: Wilken Communications Limited; Defendant: Postal Corporation of Kenya
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 527 of 2011
Procedural Posture
Civil Suit / Judgment
Outcome
judgment_for_plaintiff
Judges
SJ Chitembwe
Legal Topics
Breach of Contract, Contract Variation, Construction Contracts, Special Damages, Estoppel, Remedies for Breach
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Contract Variation Construction Contracts Special Damages Estoppel Remedies for Breach

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Wilken Communications Limited

Plaintiff

Postal Corporation of Kenya

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid variation of the contract dated 25th April, 2008.
  2. 2 Whether the parties performed their respective obligations under the contract and the variation.
  3. 3 Whether the defendant is in breach of contract for non-payment of sums due under the contract and variation.

Ratio Decidendi

The court found that the contract between the parties was validly varied by mutual agreement and conduct, despite the defendant's failure to formally execute the addendum. The plaintiff completed phases 1 to 4 in full and phase 5 to 90%, with joint inspections and certifications confirming satisfactory completion. The defendant failed to pay the outstanding sums for completed works, in breach of its contractual obligations. The court held that the defendant was estopped from denying the variation or withholding payment, as it had benefited from the works and its representatives had certified completion. The defendant's counterclaim for breach by the plaintiff was dismissed, as the...

Court Disposition

judgment_for_plaintiff

Orders

  • Judgment entered for the plaintiff against the defendant for Kshs. 6,411,784.50 inclusive of VAT.
  • Defendant to pay costs of the suit to the plaintiff.