The court found that the defendant breached the sale agreement by failing to complete the house to the standard of the sample house and by not issuing a certificate of practical completion, which was a contractual precondition for the plaintiff's payment of the balance of the purchase price. The evidence, including...

Source-derived case information.

Citation
[2018] KEHC 3981 (KLR)
Parties
Plaintiff: Winfred N. Karanja; Defendant: Regnoil Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 595 of 2014
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's claim succeeds in part; defendant's counterclaim dismissed.
Judges
AN Makau
Legal Topics
Sale of Land, Breach of Contract, Specific Performance, Remedies for Breach, Construction Defects
Source Language
en
Commercial and Corporate Land and Property Sale of Land Breach of Contract Specific Performance Remedies for Breach Construction Defects

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Winfred N. Karanja

Plaintiff

Regnoil Kenya Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a breach of contract between the plaintiff and the defendant, and if so, by whom.
  2. 2 Whether the defendant's counterclaim should be granted.
  3. 3 What reliefs, if any, are available to the plaintiff or defendant.

Ratio Decidendi

The court found that the defendant breached the sale agreement by failing to complete the house to the standard of the sample house and by not issuing a certificate of practical completion, which was a contractual precondition for the plaintiff's payment of the balance of the purchase price. The evidence, including expert reports and a site visit, established that the house had significant defects and was not finished as agreed. The plaintiff had paid a substantial portion of the purchase price and her financier's undertaking for the balance remained valid, but payment was rightfully withheld due to the defendant's non-compliance. The defendant's counterclaim failed as it was not entitled...

Court Disposition

Plaintiff's claim succeeds in part; defendant's counterclaim dismissed.

Orders

  • The cost of making good the house is Kshs. 2,150,694.52.
  • Defendant to remedy the defects as per the BQ Report within 60 days, issue certificate of completion, and hand over the premises to the plaintiff; plaintiff to pay the balance of the purchase price as per contract.