[2007] KEHC 3275 (KLR)

[2007] KEHC 3275 (KLR)

The Court of Appeal held that the High Court did not err in ordering an inter partes hearing of the application for leave to institute judicial review proceedings, as the judge has discretion to adjourn the whole application for such hearing. The Court further found that the dispute between the parties was purely...

Source-derived case information.

Citation
[2007] KEHC 3275 (KLR)
Parties
Appellant: Zakhem Construction (Kenya) Limited; Respondent: Permanent Secretary, Ministry of Roads & Public Works; Respondent: Chief Engineer, Ministry of Roads & Public Works
Court
High Court
Court Station
High Court at Embu
Jurisdiction
Kenya
Case Number
Civil Appeal 244 of 2006
Procedural Posture
Civil Appeal / Judgment on Appeal From High Court Ruling Declining Leave for Judicial Review
Outcome
Appeal dismissed with costs to the respondents.
Judges
J Wakiaga
Legal Topics
Judicial Review Leave, Contractual Termination, Remedies for Breach of Contract, Arbitration Clauses
Source Language
en
Civil Procedure Commercial and Corporate Judicial Review Leave Contractual Termination Remedies for Breach of Contract Arbitration Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Zakhem Construction (Kenya) Limited

Appellant

Permanent Secretary, Ministry of Roads & Public Works

Respondent

Chief Engineer, Ministry of Roads & Public Works

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal From High Court Ruling Declining Leave for Judicial Review

  1. 1 Whether the High Court erred in ordering inter partes hearing of an application for leave to institute judicial review proceedings, contrary to Order 53 Rule 1(2) of the Civil Procedure Rules.
  2. 2 Whether judicial review is available as a remedy for alleged breach of contract where an arbitration clause exists.
  3. 3 Whether the rules of natural justice required the respondents to hear the appellant before issuing a notice of termination under the contract.

Ratio Decidendi

The Court of Appeal held that the High Court did not err in ordering an inter partes hearing of the application for leave to institute judicial review proceedings, as the judge has discretion to adjourn the whole application for such hearing. The Court further found that the dispute between the parties was purely contractual, governed by the terms of the written agreement, including an arbitration clause. The appellant's remedy for any alleged breach of contract lay in private law, not in judicial review. The provisions of the contract did not import a public law duty to hear the appellant before termination. Accordingly, the High Court was correct in declining leave to apply for judicial...

Court Disposition

Appeal dismissed with costs to the respondents.

Orders

  • The appeal is dismissed with costs to the respondents.