[2025] KEHC 1195 (KLR)

[2025] KEHC 1195 (KLR)

The court held that the performance guarantee was a distinct contract between the interested party (bank) and the 2nd defendant, not subject to the arbitration clause in the agreements between the plaintiff and the defendants. The interested party was not bound by the arbitration clause and had only subjected itself...

Source-derived case information.

Citation
[2025] KEHC 1195 (KLR)
Parties
Plaintiff: Zhejiang Chengjian Construction Africa Limited; Defendant: Eighty Eight Nairobi Limited; Defendant: White Steid Construction Limited; Interested Party: Standard Charterred Bank (Kenya) Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Suit E547 of 2024
Procedural Posture
Commercial Suit / Ruling on Application for Temporary Injunction Pending Arbitration
Outcome
application dismissed with costs
Judges
BM Musyoki
Legal Topics
Performance Guarantees, Injunctions, Arbitration Clauses, Privity of Contract
Source Language
en
Commercial and Corporate Civil Procedure Performance Guarantees Injunctions Arbitration Clauses Privity of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Zhejiang Chengjian Construction Africa Limited

Plaintiff

Eighty Eight Nairobi Limited

Defendant

White Steid Construction Limited

Defendant

Standard Charterred Bank (Kenya) Limited

Interested Party

Procedural Posture

Commercial Suit / Ruling on Application for Temporary Injunction Pending Arbitration

  1. 1 Whether the performance guarantee is subject to the arbitration clause in the agreements between the plaintiff and the defendants.
  2. 2 Whether the plaintiff has established grounds for the grant of a temporary injunction pending arbitration.

Ratio Decidendi

The court held that the performance guarantee was a distinct contract between the interested party (bank) and the 2nd defendant, not subject to the arbitration clause in the agreements between the plaintiff and the defendants. The interested party was not bound by the arbitration clause and had only subjected itself to the non-exclusive jurisdiction of the court. The plaintiff failed to specify the nature of the dispute or demonstrate that a real dispute existed for reference to arbitration. The evidence showed that the plaintiff had breached the contract, abandoned the project, and failed to rectify defaults despite notices. The court found no justification for granting an injunction, as...

Court Disposition

application dismissed with costs

Orders

  • The application dated 10-09-2024 is dismissed.
  • Costs awarded to the defendants and the interested party.