[2018] KEELC 844 (KLR)

[2018] KEELC 844 (KLR)

The court determined that the application raised significant public interest concerns, as substantial public funds had already been invested in the construction project. The risk of further loss to the public if the contractor abandoned the work outweighed the need to maintain the status quo. The court found that...

Source-derived case information.

Citation
[2018] KEELC 844 (KLR)
Parties
Plaintiff: Zipporah Jepkemboi Korir; Plaintiff: Andrew Arap Rotich; Defendant: Ministry of Education; Defendant: Attorney General; Defendant: Elisha Busienei; Defendant: County Government of Uasin Gishu; Defendant: Belion Contractors; Defendant: Rift Valley Technical Training Institute
Court
Environment and Land Court
Court Station
Environment and Land Court at Eldoret
Jurisdiction
Kenya
Case Number
Environment & Land Case 56 of 2016
Procedural Posture
Miscellaneous Application / Ruling on Application to Set Aside Status Quo Order
Outcome
application partially allowed
Judges
A Ombwayo
Legal Topics
Status Quo Orders, Public Interest Projects, Construction Disputes
Source Language
en
Land and Property Status Quo Orders Public Interest Projects Construction Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Zipporah Jepkemboi Korir

Plaintiff

Andrew Arap Rotich

Plaintiff

Ministry of Education

Defendant

Attorney General

Defendant

Elisha Busienei

Defendant

County Government of Uasin Gishu

Defendant

Belion Contractors

Defendant

Rift Valley Technical Training Institute

Defendant

Procedural Posture

Miscellaneous Application / Ruling on Application to Set Aside Status Quo Order

  1. 1 Whether the status quo order should be set aside to allow completion of construction on the suit property.
  2. 2 Whether public interest justifies allowing the contractor to complete the project despite the ongoing dispute.

Ratio Decidendi

The court determined that the application raised significant public interest concerns, as substantial public funds had already been invested in the construction project. The risk of further loss to the public if the contractor abandoned the work outweighed the need to maintain the status quo. The court found that any loss suffered by the plaintiffs could be compensated by the state. Therefore, in the interest of justice, the court reviewed and varied its earlier order to allow the contractor to complete the construction, but directed that the handing over of the completed project should await the final decision of the court.

Court Disposition

application partially allowed

Orders

  • The contractor is allowed to complete the construction of the structure on the suit property.
  • The handing over of the completed project to the applicant shall await the final decision of the court.