Centre for Environmental Policy ( CEPA) & Others v Southern Region Water Board ( SRWB) and Another (Misc. Cause 9 of 2022) [2022] MWHC 35 (16 March 2022)

Centre for Environmental Policy ( CEPA) & Others v Southern Region Water Board ( SRWB) and Another (Misc. Cause 9 of 2022) [2022] MWHC 35 (16 March 2022)

The High Court has jurisdiction to hear the application directly under section 4 of the Environmental Management Act, 2017, notwithstanding the existence of the Environmental Tribunal. The 2nd Defendant is a proper party as the Claimants were led to sue it due to the 1st Defendant's failure to disclose relevant...

Source-derived case information.

Citation
[2022] MWHC 35
Parties
Claimant: Centre for Environmental Policy (CEPA); Claimant: National Youth Network on Climate Change (NYNCC); Claimant: Movement for Environmental Action (MEA); Defendant: Southern Region Water Board (SRWB); Defendant: Alghanim International General Trading and Contracting Company/PLEM Construction JV (AIG/PLEM)
Court
High Court of Malawi
Jurisdiction
Malawi
Case Number
Misc. Cause 9 of 2022
Procedural Posture
Civil Miscellaneous Cause / Ruling on Preliminary Objections and Interlocutory Application
Outcome
preliminary objections overruled; interlocutory injunction and disclosure order granted
Legal Topics
Interlocutory Injunctions, Access to Environmental Information, Jurisdiction of Environmental Tribunal, Legal Capacity to Be Sued, Abuse of Court Process
Source Language
en
Environmental Law Constitutional Law Administrative Law Access to Information Interlocutory Injunctions Access to Environmental Information Jurisdiction of Environmental Tribunal Legal Capacity to Be Sued +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 32 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Centre for Environmental Policy (CEPA)

Claimant

National Youth Network on Climate Change (NYNCC)

Claimant

Movement for Environmental Action (MEA)

Claimant

Southern Region Water Board (SRWB)

Defendant

Alghanim International General Trading and Contracting Company/PLEM Construction JV (AIG/PLEM)

Defendant

Procedural Posture

Civil Miscellaneous Cause / Ruling on Preliminary Objections and Interlocutory Application

  1. 1 Whether the High Court is the proper forum for the application given the existence of the Environmental Tribunal under the Environmental Management Act, 2017
  2. 2 Whether the 2nd Defendant (AIG/PLEM JV) has legal capacity to be sued
  3. 3 Whether the 2nd Defendant is a necessary party to the proceedings

Ratio Decidendi

The High Court has jurisdiction to hear the application directly under section 4 of the Environmental Management Act, 2017, notwithstanding the existence of the Environmental Tribunal. The 2nd Defendant is a proper party as the Claimants were led to sue it due to the 1st Defendant's failure to disclose relevant information. The application is not an abuse of court process as the previous proceedings were dismissed on a technicality and involved different parties and issues. The Claimants have established a serious question to be tried, damages would be inadequate, and the balance of convenience favors granting an interlocutory injunction to prevent irreparable environmental harm. The...

Court Disposition

preliminary objections overruled; interlocutory injunction and disclosure order granted

Orders

  • Defendants restrained from carrying out any works on Nkhudzi Hill pending further order or resolution of the substantive matter.
  • Defendants to provide Claimants with all requested documents, plans, studies, drawings, and impact assessment reports regarding the project within 15 days.