Nsaku and 3 Others v Lilongwe City Council (Civil Cause 810 of 2021) [2021] MWHCCiv 25 (1 November 2021)

Nsaku and 3 Others v Lilongwe City Council (Civil Cause 810 of 2021) [2021] MWHCCiv 25 (1 November 2021)

Applicants have no serious claim to pursue as the land is a road reserve, their occupation was temporary, alternative trading locations have been provided, and damages are quantifiable and adequate. It would not be just to grant the injunction as the law allows road extension works within road reserves.

Source-derived case information.

Citation
[2021] MWHCCiv 25
Parties
Claimant: Happy Nsaku; Claimant: Lustika Banda; Claimant: Mike Chibwe; Applicant: Maganga Mdala; Respondent: Lilongwe City Council
Court
High Court of Malawi Civil Division
Jurisdiction
Malawi
Case Number
Civil Cause 810 of 2021
Procedural Posture
Civil / Ruling on Application for Interlocutory Injunction
Outcome
application for injunction dismissed
Legal Topics
Injunctions, Compensation, Road Reserves, Right to Economic Activity, Legitimate Expectation
Source Language
en
Administrative Law Constitutional Law Property Law Injunctions Compensation Road Reserves Right to Economic Activity Legitimate Expectation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Happy Nsaku

Claimant

Lustika Banda

Claimant

Mike Chibwe

Claimant

Maganga Mdala

Applicant

Lilongwe City Council

Respondent

Procedural Posture

Civil / Ruling on Application for Interlocutory Injunction

  1. 1 Whether to grant an interlocutory injunction restraining the respondent from demolishing structures and evicting applicants from Lizulu Market without relocation or compensation
  2. 2 Whether applicants have a serious question to be tried regarding their right to economic activity and legitimate expectation
  3. 3 Whether damages would be an adequate remedy

Ratio Decidendi

Applicants have no serious claim to pursue as the land is a road reserve, their occupation was temporary, alternative trading locations have been provided, and damages are quantifiable and adequate. It would not be just to grant the injunction as the law allows road extension works within road reserves.

Court Disposition

application for injunction dismissed

Orders

  • application for interlocutory injunction is dismissed