Mussa v Electricity Supply Corporation of Malawi Ltd (None) [2015] MWHC 458 (29 November 2015)

Mussa v Electricity Supply Corporation of Malawi Ltd (None) [2015] MWHC 458 (29 November 2015)

Time was not of the essence in the contract, and the plaintiff was warned of possible delays. The plaintiff failed to prove the delay was unreasonable or caused by the defendant's breach. Therefore, there was no breach of contract.

Source-derived case information.

Citation
[2015] MWHC 458
Parties
Plaintiff: Mussa; Defendant: Electricity Supply Corporation of Malawi (ESCOM)
Court
High Court of Malawi
Jurisdiction
Malawi
Procedural Posture
Civil / Judgment
Outcome
Action dismissed
Legal Topics
Breach of Contract, Damages, Reasonable Time for Performance
Source Language
en
Contract Law Breach of Contract Damages Reasonable Time for Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Mussa

Plaintiff

Electricity Supply Corporation of Malawi (ESCOM)

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the defendant breached the contract by delaying electricity connection
  2. 2 Whether the defendant is liable for lost revenue and refund of interest paid on the loan

Ratio Decidendi

Time was not of the essence in the contract, and the plaintiff was warned of possible delays. The plaintiff failed to prove the delay was unreasonable or caused by the defendant's breach. Therefore, there was no breach of contract.

Court Disposition

Action dismissed

Orders

  • Plaintiff's claim for breach of contract, lost revenue, and refund of interest is dismissed
  • No damages or costs awarded to the plaintiff