Phiri v Attorney General (Civil Cause 2790 of 2003) [2004] MWHC 37 (31 May 2004)

Phiri v Attorney General (Civil Cause 2790 of 2003) [2004] MWHC 37 (31 May 2004)

The plaintiff is entitled to the value of work done, loss of profit on the balance of the contract, loss of use of equipment, demobilisation costs, extension of time, and release of bonds, as the defendant wrongfully repudiated the contract and did not challenge the assessment.

Source-derived case information.

Citation
[2004] MWHC 37
Parties
Plaintiff: P. D. Phiri t/a Malaya Building and Civil Engineering Contractors; Defendant: The Attorney General
Court
High Court of Malawi
Jurisdiction
Malawi
Case Number
Civil Cause 2790 of 2003
Procedural Posture
Civil / Assessment of Damages After Default Judgment
Outcome
damages awarded to plaintiff
Legal Topics
Damages for Breach of Contract, Assessment of Damages, Repudiation, Liquidated Damages
Source Language
en
Contract Law Damages for Breach of Contract Assessment of Damages Repudiation Liquidated Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

P. D. Phiri t/a Malaya Building and Civil Engineering Contractors

Plaintiff

The Attorney General

Defendant

Procedural Posture

Civil / Assessment of Damages After Default Judgment

  1. 1 What damages are payable to the plaintiff following the defendant's repudiation of the contract?
  2. 2 Is the plaintiff entitled to loss of profit, loss of use, demobilisation costs, and extension of time?
  3. 3 Should the bonds be released following the defendant's repudiation?

Ratio Decidendi

The plaintiff is entitled to the value of work done, loss of profit on the balance of the contract, loss of use of equipment, demobilisation costs, extension of time, and release of bonds, as the defendant wrongfully repudiated the contract and did not challenge the assessment.

Court Disposition

damages awarded to plaintiff

Orders

  • Plaintiff awarded K62,808,797.61 plus costs as damages.
  • Defendant to pay K7,144,226.35 directly to plaintiff's creditors as per schedule.