NAEB v. SINFOTEC Sarl
SINFOTEC Sarl failed to prove force majeure for the 12-day delay; thus, OCIR-THE was justified in deducting the corresponding late fee. However, OCIR-THE was not entitled to set-off 11,543,000Frw owed to SINFOTEC Sarl against a debt of another company (EIS). SINFOTEC Sarl is entitled to late fees on this amount at 0.1% per day for 1,753 days, plus reasonable counsel and procedural fees. Damages based on article 258 of the Civil Code (tort) are not applicable to contractual performance issues. The High Court erred by not specifying the amounts awarded for counsel and procedural fees before ordering compensation between parties.
- Citation
- [V.2-2005]RLR
- Parties
- Appellant/respondent: NAEB (formerly OCIR-THE); Appellant/respondent: SINFOTEC Sarl
- Court
- Supreme Court
- Jurisdiction
- Rwanda
- Judgment Date
- 25 April 2014
- Case Number
- RADA 0025/12/CS
- Procedural Posture
- Administrative Appeal / Supreme Court Judgment
- Outcome
- Both appeals allowed in part; judgment varied.
- Legal Topics
- Burden of Proof, Force Majeure, Breach of Contract, Late Fees, Damages, Set Off, Counsel Fees, Procedural Fees
- Source Language
- en, rw
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
NAEB (formerly OCIR-THE)
Appellant/respondent
SINFOTEC Sarl
Appellant/respondent
Procedural Posture
Administrative Appeal / Supreme Court Judgment
Legal Issues
- 1 Whether SINFOTEC Sarl proved force majeure for late delivery
- 2 Whether OCIR-THE was justified in deducting late fees and set-off amounts
- 3 Whether SINFOTEC Sarl is entitled to damages and late fees
Ratio Decidendi
SINFOTEC Sarl failed to prove force majeure for the 12-day delay; thus, OCIR-THE was justified in deducting the corresponding late fee. However, OCIR-THE was not entitled to set-off 11,543,000Frw owed to SINFOTEC Sarl against a debt of another company (EIS). SINFOTEC Sarl is entitled to late fees on this amount at 0.1% per day for 1,753 days, plus reasonable counsel and procedural fees. Damages based on article 258 of the Civil Code (tort) are not applicable to contractual performance issues. The High Court erred by not specifying the amounts awarded for counsel and procedural fees before ordering compensation between parties.
Court Disposition
Both appeals allowed in part; judgment varied.
Orders
- OCIR-THE (NAEB) to pay SINFOTEC Sarl 11,543,000Frw deducted without justification.
- OCIR-THE to pay SINFOTEC Sarl 20,234,000Frw as late fees (0.1% per day for 1,753 days on 11,543,000Frw).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment