ZUBACX Ltd vs OGARU CONSTRUCTION AND CONSULTANTS Ltd

ZUBACX Ltd vs OGARU CONSTRUCTION AND CONSULTANTS Ltd

ZUBACX Ltd is liable for delay damages because COVID-19 was a known risk at the time of contracting and cannot be invoked as force majeure. However, the damages must not exceed the contract value; thus, the award is reduced to 76,000,000 Frw, the contract amount. Costs and attorney fees are awarded to OGARU as the...

Source-derived case information.

Citation
RCOMAA 00036/2023/CA
Parties
Appellant: ZUBACX Ltd; Respondent: OGARU CONSTRUCTION AND CONSULTANTS Ltd
Court
Court of Appeal
Jurisdiction
Rwanda
Judgment Date
30 April 2024
Case Number
RCOMAA 00036/2023/CA
Procedural Posture
Commercial Appeal / Final Appellate Judgment
Outcome
partially allowed
Legal Topics
Liquidated Damages, Force Majeure, Contract Performance, Appeal Procedure
Contract Law Commercial Law Liquidated Damages Force Majeure Contract Performance Appeal Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

ZUBACX Ltd

Appellant

OGARU CONSTRUCTION AND CONSULTANTS Ltd

Respondent

Procedural Posture

Commercial Appeal / Final Appellate Judgment

  1. 1 Whether ZUBACX Ltd should be liable for delay damages despite invoking force majeure (COVID-19)
  2. 2 Whether the quantum of delay damages awarded was excessive and should be reduced
  3. 3 Whether costs and attorney fees should be awarded and to whom

Ratio Decidendi

ZUBACX Ltd is liable for delay damages because COVID-19 was a known risk at the time of contracting and cannot be invoked as force majeure. However, the damages must not exceed the contract value; thus, the award is reduced to 76,000,000 Frw, the contract amount. Costs and attorney fees are awarded to OGARU as the prevailing party.

Court Disposition

partially allowed

Orders

  • ZUBACX Ltd to pay OGARU CONSTRUCTION AND CONSULTANTS Ltd delay damages of 76,000,000 Frw.
  • ZUBACX Ltd to pay OGARU CONSTRUCTION AND CONSULTANTS Ltd 500,000 Frw for attorney fees and 200,000 Frw for costs at appellate level.