ARK Construction (PTY) Ltd v Veatel (PTY) Ltd (10869/2020) [2022] ZAGPJHC 441 (3 May 2022)
- Citation
- [2022] ZAGPJHC 441
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- South Gauteng High Court, Johannesburg
- Panel
- Crutchfield
- Case number
- 10869/2020
More details
- Court
- South Gauteng High Court, Johannesburg
- Panel
- Crutchfield
- Case number
- 10869/2020
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the respondent had set out sufficient facts to dispute the applicant's claim on bona fide and reasonable grounds. The respondent's dispute regarding the terms of the agreement and the extent of services rendered was supported by reference to invoices and the structure of payment for completed work. The respondent was not required to prove its defence or present all evidence at this stage, only to raise reasonable grounds for dispute. The court also considered that granting a winding-up order after the applicant had received payment of over R1.4 million would unfairly favour one creditor over others. Consequently, the interests of justice did not warrant a provisional winding-up order. The respondent was ordered to pay the costs due to the lateness of its tender.
Court disposition
Application dismissed; respondent ordered to pay costs.
Orders
- The application is dismissed.
- The respondent is ordered to pay the costs of the application.
02
Material facts
Parties
ARK Construction (PTY) Ltd
Applicant Counsel: Ms N LombardVeatel (PTY) Ltd
Respondent Counsel: Mr FW Botes SC and Mr C van GassAmounts and remedies
- Applicant's Claimed Debt: ZAR 4,425,529.5
- Respondent's Admitted Payment: ZAR 1,457,539.69
03
Procedural history
Posture
Winding Up Application / Hearing and Judgment
04
Questions and positions
Legal issues
- 01
Whether the respondent is indebted to the applicant in an amount exceeding R100 and unable to pay its debts.
- 02
Whether the respondent's dispute of indebtedness is bona fide and reasonable.
- 03
Whether it is just and equitable to grant a provisional winding-up order against the respondent.
- 04
Whether the applicant is entitled to costs given the respondent's late tender of payment.
Party arguments
- Applicant
- The applicant argued that the respondent owed it R4,425,529.50 for construction services rendered, which remained due and payable. The applicant contended that the respondent failed to pay, secure, or compound the debt within the statutory 21-day period after demand in terms of section 345(1) of the Companies Act 61 of 1973. The applicant maintained that the respondent's dispute regarding the balance of the indebtedness was without merit and that it had a statutory right to winding-up under section 345, as approximately R3 million remained unpaid. The applicant relied on the Carstens report, asserting that not all invoices were considered and that the respondent failed to provide third-party contractor invoices allegedly used to complete the work.
- Respondent
- The respondent admitted indebtedness of R1,457,539.69 and tendered payment, which was made before the hearing. It disputed liability for the balance, raising several grounds: the terms of the partly oral, partly written agreement; the extent of services rendered, particularly regarding CAC invoices and meters completed; the existence of an oral agreement concerning interest on the Enable factoring agreement; and the overall indebtedness. The respondent argued that its dispute was bona fide and reasonable, that it was unwilling rather than unable to pay, and that winding-up would unfairly favour one creditor over others. It maintained that it was not obliged to present all evidence at this stage and that the applicant failed to set out the written portions of the agreement.
05
Court’s reasoning
Legal principles
- 01
Kalil v Decotex (Pty) Ltd & Another 1988 (1) SA 943 (AD)
A respondent need only show that its indebtedness is disputed on bona fide and reasonable grounds, not that it is not indebted at all.
- 02
Badenhorst v Northern Construction Enterprises (Pty) Ltd 1956 (2) SA 346 (T) at 347H – 348B
The Badenhorst Rule requires that a winding-up order should not be granted where the respondent disputes the debt on bona fide and reasonable grounds.
- 03
GAP Merchant Recycling CC v Goal Reach Trading 55 CC 2016 (1) SA 261 (WCC)
The test for provisional winding-up is whether the applicant meets the requirements on a prima facie basis, considering the balance of probabilities on all affidavits.
- 04
Hulse-Reutter & Another v HEG Consulting Enterprises (Pty) Ltd (Lane v Fey NNO intervening) 1998 (2) SA 208 (C) at 219F – 220C
At this stage, the respondent does not have to prove its defence or adduce all evidence; it must set out grounds that are not unreasonable and on which it disputes the claim.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the respondent had set out sufficient facts to dispute the applicant's claim on bona fide and reasonable grounds. The respondent's dispute regarding the terms of the agreement and the extent of services rendered was supported by reference to invoices and the structure of payment for completed work. The respondent was not required to prove its defence or present all evidence at this stage, only to raise reasonable grounds for dispute. The court also considered that granting a winding-up order after the applicant had received payment of over R1.4 million would unfairly favour one creditor over others. Consequently, the interests of justice did not warrant a provisional winding-up order. The respondent was ordered to pay the costs due to the lateness of its tender.
Obiter and limits
- The respondent's failure to attach invoices for the alleged cost of completing the CWC work cast doubt on the reasonable basis of its counterclaim, but this did not defeat its bona fide dispute.
- The interests of justice require consideration of the impact of winding-up on all creditors, not just the applicant.
Court disposition
Application dismissed; respondent ordered to pay costs.
- The application is dismissed.
- The respondent is ordered to pay the costs of the application.
Source and reliance status
South Gauteng High Court, Johannesburg
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
South Gauteng High Court, Johannesburg
Judgment
IN THE HIGH COURT OF SOUTH AFRICA,
GAUTENG LOCAL DIVISION, JOHANNESBURG
CASE NO: 10869/2020
REPORTABLE:
NO
OF INTEREST TO OTHER JUDGES: NO
REVISED.
3 May 2022
In the matter between:
ARK CONSTRUCTION (PTY) LTD
(Registration No: 2016/347605/07
Applicant
and
VEATEL (PTY) LTD
(Registration No: 2017/271009/07)
Respondent
JUDGMENT
CRUTCHFIELD J:
[1] The applicant, Ark Construction (Pty) Ltd, sought an order of provisional winding-up, alternatively final winding-up placing the respondent, Veatel (Pty) Ltd, in the hands of the Master of the High Court.
[2] The applicant alleged that the respondent owed it an amount of R4 425 529.50 for construction services rendered at the respondent’s instance and which amount remained due and payable to the applicant.
[3] On 4 December 2020, the applicant made demand upon the respondent in terms of s 345(1)(a) and (c) of the Companies Act 61 of 1973 (as amended) (‘the Act’). The demand was served by the sheriff on 4 December 2020. The respondent failed to pay, secure or compound the indebtedness within the 21-day period in terms of s 345(1) of the Act or at all.
[4] The respondent’s attorney remitted correspondence alleging a ‘bona fide dispute’. Notwithstanding, the applicant proceeded with this application for the respondent’s winding-up. The respondent opposed the application.
[5] At the hearing of the application on Monday, 25 April 2022, the respondent tendered payment of an amount of R1 457 539.69 in respect of which it admitted its indebtedness to the applicant. The admission arose pursuant to an assessment of the work completed by the applicant, conducted by a chartered accountant, one P J Carstens.
[6] The application stood down until Thursday, 28 April 2022, for the respondent to pay the tendered amount of R1 457 539.69 (‘the tendered amount’) to the applicant’s
attorney’s trust account, which duly transpired.
[7] At the hearing on 28 April 2022, the applicant’s counsel persisted with the application on the basis that the respondent’s alleged dispute of fact in respect of the balance of the respondent’s indebtedness to the applicant was devoid of merit. Furthermore, that the applicant had a statutory right to the winding-up of the respondent in terms of s 345 of the Act given that an amount of approximately R3 million remained due and payable to the applicant.
[8] The applicant referred in particular to the report of P J Carstens (‘the Carstens report’), which reflected that Carstens had not considered all of the applicant’s invoices for work performed by the applicant, and that the respondent had not placed the invoices of third party contractors, allegedly utilised to complete the work that the applicant did not attended to adequately, (being invoices that the respondent must have had in its possession when it deposed to its answering affidavit), before the Court.
[9] The respondent’s answer was that it was not obliged to place the entirety of its evidence before this Court.
[10] The applicant is obliged to show that the respondent is indebted in an amount of more than R100.00, which amount is due and payable and that the respondent is unable to pay its debts.
[11] The respondent sought to differentiate between an inability and an unwillingness to pay its debts, contending that the latter applied in this instance pursuant to the dispute of fact that militated against a court ordering its winding-up.
[12] The test to be applied in respect of a provisional winding-up based on s 344 of the Act is whether the requirements are met on a prima facie basis by the applicant, regard being had to whether the balance of probabilities on all of the affidavits favour the applicant’s case.
[13] The respondent raised various grounds, allegedly reasonable and bona fide, on which it disputed its liability and indebtedness to the applicant. These were:
13.1 In terms of the partly oral partly written agreement entered into between the parties;
13.2 The extent of the services rendered by the applicant, specifically in relation to the CAC invoices and the actual meters claimed to have been completed by the applicant;
13.3 The existence of an ostensible oral agreement in relation to the respondent’s purported liability for interest on the factoring agreement of Enable; and
13.4 The indebtedness by the respondent to the applicant.
[14] It is well to remember that the respondent has to show only that its indebtedness is disputed on bona fide and reasonable grounds.[1] The respondent does not have to demonstrate that it is not indebted at all to the applicant.[2]
[15] The respondent contended that the terms of the partly written partly oral agreements concluded by the parties were disputed and that the applicant failed to set out the written portions of the agreement concluded between the parties.
[16] The respondent alleged that the terms of the agreement that were disputed were that the applicant, on the respondent’s version, was entitled to 75% of R140 per meter of the work performed, after completion of the CWC certificates, after which the outstanding 25% of R140 per meter of work performed would fall due and payable after completion of the CAC certificates, which the respondent alleged the applicant did not complete. In addition, the respondent contended that the applicant did not complete the CAC works.
[17] In the light of the Kalil v Decotex and Badenhorst authorities referred to above, my task is to determine only whether the disputes of fact raised by the respondent are bona fide disputed on reasonable grounds.
[18] As to the reasonable grounds of the disputed terms of the agreement, the respondent pointed to the fact that the invoices issued by the applicant and on which it relied, correlated with the terms of the agreement relied on by the respondent. The respondent referred in this regard to annexure FA5 to the applicant’s founding affidavit, calculated and based on 75% of R140 per metre of completed work or R105 per metre, being the terms alleged by the respondent in
respect of the CWC works.
[19] In addition, the respondent referred to annexure FA19 to the applicant’s founding affidavit, allegedly calculated at the rate of 25% of R140 per metre of completed work or R35 per metre, being the terms agreed upon in respect of the CAC works as alleged by the respondent.
[20] Given the above-mentioned, the dispute raised by the respondent in respect of the terms of the agreement on which the parties contracted, is raised on grounds that are reasonable and that if proven at the trial would constitute a defence to the applicant’s claim.[3]
[21] Similarly, the respondent disputes the extent of the services rendered by the applicant and in respect of which it contends an entitlement to payment. The respondent contends that the applicant only performed in respect of the CWC works, which the applicant allegedly did partially, until termination of the agreement.
[22] The respondent allegedly had to employ third party contractors to complete the CWC works and also the CAC works. The respondent contended that the applicant did not perform any of the CAC work.
[23] The alleged cost to the respondent of completing the CWC work, being an amount of R77 883.81, was not supported by an invoice or invoices attached to the respondent’s answering affidavit and nor were details of the computation of the amount furnished by the respondent, thus casting doubt on the reasonable basis of the respondent’s alleged counterclaim.
[24] However, the respondent does not have to prove its defence or adduce the evidence upon which it will rely at the trial in these proceedings. All that the respondent has to do at this stage is set out grounds that are not unreasonable and on which the respondent disputes the applicant’s claim.[4]
[25] In my view the respondent has set out sufficient facts, even taking account of the issues raised by the applicant, such as to meet the onus resting on the respondent to show that it disputes the applicant’s claim on grounds that are both bona fide and reasonable.
[26] In addition, however, the respondent contended that to wind up the respondent, even provisionally, at the instance of the applicant after the applicant received payment of an amount exceeding R1 400 000.00, would be to favour one creditor above the balance of the respondent’s creditors. I am in agreement with that contention.
[27] In the circumstances and by reason of the aforementioned, it is not in the interests of justice for the respondent to be provisionally wound up and an order in these terms will follow hereunder.
[28] In respect of the costs of the application, the respondent’s tender of payment was made on the morning on which the matter was called.
[29] In the circumstances, given the lateness of the tender on the part of the respondent, it is appropriate that the respondent be ordered to pay the costs of the application.
[30] Accordingly, I grant the following order:
1. The application is dismissed.
2. The respondent is ordered to pay the costs of the application.
I hand down the judgment.
CRUTCHFIELD
J
JUDGE
OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION
JOHANNESBURG
Electronically submitted therefore unsigned
Delivered: This judgment was prepared and authored by the Judge whose name is reflected and is handed down electronically by circulation to the Parties / their legal representatives by email and by uploading it to the electronic file of this matter on CaseLines. The date of the judgment is deemed to be 3 May 2022.
COUNSEL FOR THE APPLICANT: Ms N Lombard.
INSTRUCTED BY:
Van Zyl Johnson Attorneys.
COUNSEL FOR THE RESPONDENT: Mr FW Botes SC
and Mr C van Gass.
INSTRUCTED BY:
Steenkamp Van Niekerk Inc Attorneys.
DATE OF THE HEARING:
25 and 28 April 2022.
DATE OF JUDGMENT:
3 May 2022.
[1] Kalil v Decotex (Pty) Ltd & Another 1988 (1) SA 943 (AD).
[2] The ‘Badenhorst Rule;’ Badenhorst v Northern Construction Enterprises (Pty) Ltd 1956 (2) SA 346 (T) at 347H – 348B.
[3] GAP Merchant Recycling CC v Goal Reach Trading 55 CC 2016 (1) SA 261 (WCC).
[4] Hulse-Reutter & Another v HEG Consulting Enterprises (Pty) Ltd (Lane v Fey NNO intervening) 1998 (2) SA 208 (C) at 219F – 220 C.
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.