Competition Commission v Isipani Construction (Pty) Ltd and Another (CR128Nov14) [2016] ZACT 88; [2016] 2 CPLR 516 (CT) (18 July 2016)
Isipani Construction admitted to two separate instances of cover pricing with Neil Muller Construction, constituting contraventions of section 4(1)(b) of the Competition Act. The Tribunal found that each instance was a distinct infringement but, in the interest of fairness and proportionality, imposed a single administrative penalty for both. The Tribunal applied the six-step penalty determination process, using Isipani's total turnover for the financial year ended 30 June 2012 as the basis. The base amount was set at 12% of turnover, discounted from the upper bound due to the lack of direct profit and mitigating factors such as Isipani being a first-time offender and pleading guilty....
- Citation
- [2016] ZACT 88
- Parties
- Applicant: Competition Commission; Respondent: Isipani Construction (Pty) Ltd; Respondent: Neil Muller Construction (Pty) Ltd
- Court
- Competition Tribunal
- Jurisdiction
- South Africa
- Judgment Date
- 18 July 2016
- Case Number
- CR128Nov14
- Procedural Posture
- Administrative Penalty Application / Penalty Determination After Admission of Contravention
- Outcome
- Isipani Construction was found to have contravened section 4(1)(b) of the Competition Act by engaging in two instances of cover pricing and was ordered to pay an administrative penalty.
- Judges
- A Wessels, M Mokuena, A Roskam
- Legal Topics
- Collusive Tendering, Cover Pricing, Administrative Penalty, Corporate Leniency Policy, Bid Rigging
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Competition Commission
Applicant
Isipani Construction (Pty) Ltd
Respondent
Neil Muller Construction (Pty) Ltd
Respondent
Procedural Posture
Administrative Penalty Application / Penalty Determination After Admission of Contravention
Legal Issues
- 1 Whether Isipani Construction contravened section 4(1)(b) of the Competition Act by engaging in cover pricing with Neil Muller Construction.
- 2 Whether the administrative penalty should be calculated for each contravention or as a single penalty.
- 3 What is the appropriate quantum of the administrative penalty under section 59 of the Competition Act.
Ratio Decidendi
Isipani Construction admitted to two separate instances of cover pricing with Neil Muller Construction, constituting contraventions of section 4(1)(b) of the Competition Act. The Tribunal found that each instance was a distinct infringement but, in the interest of fairness and proportionality, imposed a single administrative penalty for both. The Tribunal applied the six-step penalty determination process, using Isipani's total turnover for the financial year ended 30 June 2012 as the basis. The base amount was set at 12% of turnover, discounted from the upper bound due to the lack of direct profit and mitigating factors such as Isipani being a first-time offender and pleading guilty....
Court Disposition
Isipani Construction was found to have contravened section 4(1)(b) of the Competition Act by engaging in two instances of cover pricing and was ordered to pay an administrative penalty.
Orders
- Isipani Construction (Pty) Ltd is ordered to pay an administrative penalty of R21,783,153.40 for both contraventions of the Competition Act.
- No order as to costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment