Du Preez v Tornel Props (Pty) Ltd (20714/14) [2015] ZASCA 134 (29 September 2015)
The Supreme Court of Appeal held that the contractor was justified in withholding performance due to the employer's refusal to make progress payments as required by the contract. The employer's stance that payment was only due upon completion was contrary to the express terms. The subsequent cancellation by the employer was objectively a repudiation, which the contractor was entitled to accept and cancel the contract. The quantum of damages awarded by the court a quo was not proved by admissible evidence, as the Neobuild quotation was not supported by expert testimony. The parties agreed that R104,817 was a justifiable amount for damages, and the court awarded this sum. Costs were awarded...
- Citation
- [2015] ZASCA 134
- Parties
- Appellant: Lorraine Du Preez; Respondent: Tornel Props (Pty) Ltd
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 29 September 2015
- Case Number
- 20714/14
- Procedural Posture
- Civil Appeal / Appeal From North Gauteng High Court, Pretoria
- Outcome
- Appeal partly upheld; order of the court a quo set aside and replaced.
- Judges
- Shongwe, Saldulker, Swain, Mbha, Baartman
- Legal Topics
- Building Contract, Repudiation, Reciprocal Obligations, Quantum of Damages, Progress Payments
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lorraine Du Preez
Appellant
Tornel Props (Pty) Ltd
Respondent
Procedural Posture
Civil Appeal / Appeal From North Gauteng High Court, Pretoria
Legal Issues
- 1 Was the contractor justified in withholding performance under the building contract?
- 2 Did the conduct of the employer constitute repudiation entitling cancellation?
- 3 Was the quantum of damages proved by admissible evidence?
Ratio Decidendi
The Supreme Court of Appeal held that the contractor was justified in withholding performance due to the employer's refusal to make progress payments as required by the contract. The employer's stance that payment was only due upon completion was contrary to the express terms. The subsequent cancellation by the employer was objectively a repudiation, which the contractor was entitled to accept and cancel the contract. The quantum of damages awarded by the court a quo was not proved by admissible evidence, as the Neobuild quotation was not supported by expert testimony. The parties agreed that R104,817 was a justifiable amount for damages, and the court awarded this sum. Costs were awarded...
Court Disposition
Appeal partly upheld; order of the court a quo set aside and replaced.
Orders
- The defendant is ordered to pay the plaintiff the sum of R104,817.
- The defendant is ordered to pay interest thereon from 1 June 2007 to date of final payment at the rate of 15.5% per annum.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment