Du Preez v Tornel Props (Pty) Ltd (20714/14)
Du Preez v Tornel Props (Pty) Ltd (20714/14) [2015] ZASCA 134 (29 September 2015)
The Supreme Court of Appeal held that refusal to make progress payments justified the contractor’s withholding of work and the employer’s cancellation was repudiatory.
- Building Contract
- Repudiation
- Reciprocal Obligations
- Quantum Of Damages
- Progress Payments
- Building-contract