Fourie v Leong (63/84) [1984] ZASCA 62 (29 May 1984)
- Citation
- [1984] ZASCA 62
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Supreme Court of Appeal
- Panel
- Miller, Cillié, Grosskopf
- Case number
- 63/84
More details
- Court
- Supreme Court of Appeal
- Panel
- Miller, Cillié, Grosskopf
- Case number
- 63/84
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the pleadings and evidence established the existence of a valid and enforceable building contract between the parties. The appellant's plea admitted the contract and sought rectification, which signified consensus. The evidence, including correspondence and conduct, confirmed the parties' recognition of the agreement. The appellant's subsequent repudiation was clear, and the respondent was entitled to damages. The expert evidence of the quantity surveyor was accepted as adequate for determining the quantum of damages, despite minor modifications to the plans and imponderables inherent in construction cost estimation. The trial court was justified in accepting the expert's assessment and awarding damages accordingly. The appeal was dismissed.
Court disposition
Appeal dismissed with costs.
Orders
- The appeal is dismissed with costs.
02
Material facts
Parties
J S Fourie
AppellantSydney Leong
RespondentAmounts and remedies
- Damages Awarded: ZAR 17,780
- Contract Price: ZAR 27,870
- Market Cost of Construction: ZAR 45,650
03
Procedural history
Posture
Civil Appeal / Appeal From Trial Court Judgment
04
Questions and positions
Legal issues
- 01
Whether a valid and enforceable building contract existed between the parties.
- 02
Whether the respondent established the quantum of damages resulting from the appellant's repudiation.
- 03
Whether the appellant was entitled to rectification of the contract.
Party arguments
- Applicant
- The appellant argued that no valid or enforceable building contract came into existence due to lack of consensus on all material terms. Alternatively, he contended that the respondent failed to prove the quantum of damages suffered. He also sought rectification of the contract to reflect the parties' true agreement, asserting that a key clause regarding commencement of building activities was omitted due to common error.
- Respondent
- The respondent maintained that a binding building contract was concluded, evidenced by the signed documents and subsequent conduct of both parties. He asserted that the appellant repudiated the contract by refusing to perform at the agreed price. Regarding damages, the respondent relied on expert evidence from a quantity surveyor to establish the fair and reasonable cost of procuring the erection of the dwelling after repudiation, and claimed the difference between the contract price and the market cost.
05
Court’s reasoning
Legal principles
- 01
General principles of South African contract law
A party who repudiates a valid contract is liable for damages representing the difference between the contract price and the fair market cost of performance.
- 02
South African law of contract
Rectification of a contract is only available where there is clear evidence of a common intention not reflected in the written agreement.
- 03
South African law of contract
Consensus ad idem is required for the formation of a valid contract.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the pleadings and evidence established the existence of a valid and enforceable building contract between the parties. The appellant's plea admitted the contract and sought rectification, which signified consensus. The evidence, including correspondence and conduct, confirmed the parties' recognition of the agreement. The appellant's subsequent repudiation was clear, and the respondent was entitled to damages. The expert evidence of the quantity surveyor was accepted as adequate for determining the quantum of damages, despite minor modifications to the plans and imponderables inherent in construction cost estimation. The trial court was justified in accepting the expert's assessment and awarding damages accordingly. The appeal was dismissed.
Obiter and limits
- Minor deviations from original specifications in construction contracts do not necessarily undermine the validity of expert cost assessments.
- Imponderables in building operations, such as delays or unforeseen contingencies, are inherent and must be reasonably estimated in damage quantification.
Court disposition
Appeal dismissed with costs.
- The appeal is dismissed with costs.
Source and reliance status
Supreme Court of Appeal
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Supreme Court of Appeal
Judgment
380/82
N.v.H.
J S FOURIE / SYDNEY LEONG
MILLER, JA :-
380/82 N.v.H.
IN THE SUPREME COURT OF SOUTH AFRICA
(APPELLATE DIVISION)In the matter between :J S FOURIE Appellant
and
SYDNEY LEONG Respondent
CORAM: MILLER, CILLIé, JJA,
et GROSSKOPF, AJA
HEARD: 21 MAY 1984
DELIVERED: 29 MAY 1984
JUDGMENT
MILLER, JA :_
The respondent successfully sued theappellant in the Witwatersrand Local Division for payment
of / .
2 of damages suffered by reason of the appellant's repudiation of a building contract concluded by the parties for the erection of a dwelling for respondent, which repudiation the respondent accepted. In further particulars supplied at the appellant's request, the respondent explained that the damage suffered and claimed by him (R20 130) represented the difference between the contract price of the erection of the dwelling (R27 870) and the "fair and reasonable cost" of procuring the erection of such building (R48 000) after repudiation of the contract by the appellant. The trial Court (PHILIPS, AJ) entered judgment for the respondent in the sum of R17 780, with costs, and granted certain ancillary relief. The appellant appeals against the
whole / 3 whole of the order.Two main grounds of appeal are relied on by the appellant: (1) that no valid or enforceable building contract between the parties came into being because there was no true "consensus", and (2) that in any event, the respondent failed to establish the quantum of any damage he may have suffered. The first of these grounds is startlingly at odds with the plea filed by the appellant in the Court a quo; a plea upon which the parties went to trial and which has at no time been amended. It is necessary to examine that plea in some detail.
Paragraph 2 of the plea contains an admission that appellant signed a printed building contract form
and /
4and handed it to the respondent, and a statement that prior thereto he, the appellant, had handed to the respondent a written tender for the erection of a dwelling on the respondent's land, a copy of which tender was annexed to the plea. Also annexed to the plea was a written "memorandum of agreement" between the appellant as "the contractor" and the respondent as "the owner", duly signed by both parties. It was alleged in para 2 of the plea that it had at all relevant times been the common purpose of the parties to enter into a written building contract in the event of the respondent accepting the appellant's written tender and that such contract would contain a clause to the effect that the building activities would commence within
sixty / 5 sixty days of acceptance of the tender or of signing of the building contract. A further allegation in para 2 of the plea was that as a result of a common error the standard building contract signed by the appellant and thereafter handed to the respondent for signature, did not contain such clause. In consequence of all this, so it was pleaded, the appellant was entitled to rectification of the building contract annexed to the plea so that such contract would correctly reflect the agreement between the parties.I pause here to observe that para 2 of the plea, the essential terms of which I have just described, if not in express terms then very clearly by implication admits the fundamental allegation in the respondent's
particulars / 6
particulars of claim that the parties entered into a building contract, in terms of which the appellant undertook to erect a dwelling on the respondent's property for an agreed price. The unequivocal assertion that the appellant is entitled to rectification of the building contract annexed to his plea signifies recognition and acceptance by the appellant that full "consensus" was reached by the parties.In para 2 A of the plea, the appellant pleads that if the Court should find that he is not entitled to rectification of the agreement in the respect mentioned, then no valid or enforceable contract came into existence, by reason of the absence of consensus concerning each and every material term ("iedere en
elke /
7 elke wesenlike term") of the agreement. This para is said to be in the alternative to para 2. But in para 3, after denying that he repudiated the agreement ("die ooreenkoms") and pleading that the agreement fell away ("verval het") the appellant alleged in the alternative that if the building contract did not fall away, as alleged, then during May 1980 the parties verbally agreed to cancellation of their agreement ("dat die boukontrak by wyse van 'n mondelinge ooreenkoms tussen die partye gekanselleer is"). And finally, the plea concludes with a prayer (not in the alternative, but in the light of all that has preceded it) that the agreement be rectified in the respect mentioned earlier and that the respondent's claim be
dismissed / . ... 8
dismissed with costs. To the very end of the pleading,therefore, the existence of a building contractbetween the parties is recognized.
That such an agreement was in fact concludedappears, however, not only from the pleadings but fromthe evidence led on behalf of the respondent. I donot think it necessary to refer in detail to theevidence, which was reasonably fully described in the
judgment a quo. It is sufficient to say that theevidence reveals very clearly that after the signingof the written contract discussions took place between
the respondent and representatives of the appellant,
and that there was correspondence, all of which confirmsbeyond doubt the recognition by both parties of an
existing / 9 existing and enforceable building agreement for the erection by appellant of a dwelling on the respondent's property. There was clearly consensus regarding the essential terms of the contract. It also emerges very clearly from such discussions that the appellant discovered that the price for which he had agreed to erect the dwelling was inadequate; he was not prepared to carry out his undertaking for that price. The respondent, though not obliged to do so, was prepared to meet the appellant to an extent by accepting liability for an increased price but such offer was unacceptable to the appellant who clearly repudiated the contract by refusing to execute the work he had undertaken to do. There was no refutation of respondent's evidence in those
respects / 10
respects, for the appellant, after unsuccessfully applying for absolution from the instance at the close of the respondent's case, closed his case without giving or leading any evidence at all. The allegations in the plea relating to the falling away of the agreement, or its cancellation by the oral agreement of the parties, therefore remain empty shells and are of no avail. There is no substance in the argument that the respondent failed to establish the agreement pleaded by him and it is very clear that the appellant is liable to the respondent for such loss or damage as the latter sustained by reason of the appellant's repudiation of the agreement. This brings me, then, to the second of the grounds upon which it was contended on behalf of the appellant
that / 11
that the respondent ought to have been non-suited, i.e.,the ground that respondent failed adequately toestablish the quantum of his alleged loss or damage.In the main, the evidence relied upon for determination of the quantum of the damage suffered by the respondent was that of Mr Schloss. He is a qualified and registered quantity surveyor and at the time of giving evidence was head of the department of building management in the University of the Witwatersrand and also practised as a quantity surveyor in a consultant capacity. He was also the editor of a publication known as the "Builders Pricing Manual". He was engaged by the respondent to assess "the fair and reasonable market
cost /
12 cost" of erecting a dwelling such as the appellant had undertaken to erect for the respondent. He explained that in order to arrive at such cost he carried out an inspection of the site, took measurements and prepared a schedule of "all the finishes to the various rooms". He measured the plan of the building on a "rough quantity system" and then priced the quantities required at the average rates pertaining to the building industry at the particular time. He had considerable personal knowledge of the prices of building materials from the exercise of his profession and where he was uncertain he made inquiries in order to establish as nearly as possible the average prices of materials.
He / 13
He prepared a rough bill of quantities consistingof thirty pages which was available for inspectionby the appellant and his advisers. The cost at whichthe witness arrived was R46 000 but he deductedtherefrom the sum of R350 when an error of one metrein regard to the length of a wall was brought to hisnotice, thus leaving a total sum of R45 650.
Included in the total sum were provisional sums inrespect of kitchen cupboards, light fittings and floorcoverings. The items were as taken from the originalcontract and specifications but the prices were takenat their "escalated" market cost at the time of hissurvey. What were not included in his total estimatewere professional fees and allied costs, any special
foundations, excavations in hard or soft rock and
municipal /
14
municipal fees.The appellant's main criticism of the evidence of Schloss was that he had not made his cost determination strictly upon the basis of the original specifications. The respondent had engaged other contractors to build the desired dwelling for him and such dwelling was said to have differed in certain respects from the dwelling which was the subject of the building contract and specifications signed by the parties. Schloss admitted in evidence that there were
"slight modifications" of the original plans and speci=
fications in the house that was later built but said
that when estimating the "fair and reasonable market
cost", which he was engaged to do, he "ignored the
changes" /
15
changes" in the newly-constructed house and based hisestimates on the contract drawing in his possessionand the original specification and the schedule offinishes. Such deviations as there might have beenfrom the initial specifications or plans were relativelyminor, and would have no significant bearing on thecosts. And where in the newly-built house there weremore expensive materials than had originally been
specified (e.g. Harvey tiles instead of ordinary tiles),
the price of the materials originally specified was
taken into consideration for purposes of estimating the
cost of the dwelling. Schloss also explained that in
arriving at the total cost of construction he had allowed
for a profit-margin for the contractor of between 10%
and / 16
and 15%; i.e., the lower percentage in respect of certain items and the higher in respect of other items.I am satisfied that the evidence of Schloss was more than adequate to enable the Court to make a proper assessment of the quantum of the damage suffered by the respondent. It must be remembered that although many of the items going towards the determination of the total cost of construction might permit of accurate calculation (e.g. the quantity and price of materials), there are inevitably imponderables in the assessment of the total cost, which can at best be estimated, not minutely calculated. I have in mind, for example, the duration of the building operations and how this might be affected by delays in the supply of materials
or by / 17 or by inclement weather or other factors; the emergence of unforeseen contingencies in excavations, the encountering of rock, and so on. It is noteworthy that such provisional items were not taken into account in the estimation of final cost. If occasional variations of the original schedules might have caused some slight additional cost, this would probably have been over-compensated by the omission to take into account at all other provisional items. But, however that may be, it appears to me that in the light of the detailed and unrefuted evidence of Schloss, it cannot be said that the trial Court was not entitled to accept the determination made by Schloss and to make an award accordingly.
The /
18 The appeal is dismissed with costs.
S MILLER JUDGE OF APPEAL
CILLIé JA )) CONCUR GROSSKOPF, AJA )
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.