Gcwabe Consulting (Pty) Ltd v South African Police Service (46817/2015) [2022] ZAGPPHC 993 (17 August 2022)
- Citation
- [2022] ZAGPPHC 993
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- North Gauteng High Court, Pretoria
- Panel
- N Janse van Nieuwenhuizen
- Case number
- 46817/2015
More details
- Court
- North Gauteng High Court, Pretoria
- Panel
- N Janse van Nieuwenhuizen
- Case number
- 46817/2015
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that since the contract had been declared invalid, allowing the plaintiff to pursue damages for loss of income for the remaining contract period would result in an undue benefit from an invalid contract. The facts differed from Buffalo City, as the plaintiff sought damages beyond accrued rights. The just and equitable remedy was to set aside the contract entirely, thereby extinguishing any further claims under it. The plaintiff, having pursued the matter despite the contract's invalidity, was ordered to pay costs, including those of two counsel and reserved costs.
Court disposition
The contract between the parties is set aside. The plaintiff is ordered to pay the costs, including the costs of two counsel and reserved costs.
Orders
- The contract between the parties is set aside.
- The plaintiff is ordered to pay the costs, which include the costs of two counsel and the costs reserved on 10 August 2022.
02
Material facts
Parties
Gcwabe Consulting (Pty) Ltd
Plaintiff Counsel: I MureriwaSouth African Police Service
Defendant Counsel: JL Van der Merwe SCAmounts and remedies
- Plaintiff's Claimed Damages: ZAR 50,858,579.43
03
Procedural history
Posture
Civil Trial / Remedy and Costs After Declaration of Contract Invalidity
04
Questions and positions
Legal issues
- 01
What is the appropriate just and equitable remedy after the contract was declared invalid.
- 02
Should the contract be set aside or should accrued rights be preserved.
- 03
Is the plaintiff entitled to damages for loss of income under the invalid contract.
- 04
Who should bear the costs of the proceedings.
Party arguments
- Applicant
- The plaintiff argued that it acted in good faith and should not be penalized with costs, as it was the innocent party. It claimed damages for loss of income due to the defendant's breach or repudiation, asserting entitlement to compensation for the remaining contract period.
- Respondent
- The defendant contended that the plaintiff was in breach of contract, failed to rectify the breach, and that the contract was validly cancelled. It argued that the plaintiff had already been paid for all work performed and that damages for future income under an invalid contract would result in undue benefit. The defendant also sought costs, having succeeded in its counterclaim.
05
Court’s reasoning
Legal principles
- 01
Constitution of the Republic of South Africa, 1996
Section 172(1)(b) of the Constitution empowers the court to make any order that is just and equitable when a contract is declared invalid.
- 02
Buffalo City Metropolitan Municipality v Asia Construction (Pty) Ltd 2019 (4) SA 331 (CC)
Where a contract is declared invalid, accrued rights may be preserved, but no further rights may be obtained under the invalid contract.
06
Ratio, limits and disposition
Ratio decidendi
The court found that since the contract had been declared invalid, allowing the plaintiff to pursue damages for loss of income for the remaining contract period would result in an undue benefit from an invalid contract. The facts differed from Buffalo City, as the plaintiff sought damages beyond accrued rights. The just and equitable remedy was to set aside the contract entirely, thereby extinguishing any further claims under it. The plaintiff, having pursued the matter despite the contract's invalidity, was ordered to pay costs, including those of two counsel and reserved costs.
Obiter and limits
- The plaintiff's argument regarding innocence and good faith would have been more persuasive had it not continued to pursue the matter after the plea of invalidity.
- Officials in the employ of the defendant failed to follow the prescribed procurement process, but this does not absolve the plaintiff from the consequences of the contract's invalidity.
Court disposition
The contract between the parties is set aside. The plaintiff is ordered to pay the costs, including the costs of two counsel and reserved costs.
- The contract between the parties is set aside.
- The plaintiff is ordered to pay the costs, which include the costs of two counsel and the costs reserved on 10 August 2022.
Source and reliance status
North Gauteng High Court, Pretoria
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
North Gauteng High Court, Pretoria
Judgment
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG DIVISION, PRETORIA)
Case Number: 46817/2015
REPORTABLE:
NO
OF INTEREST TO OTHER JUDGES: NO
REVISED:
YES
17 AUGUST 2022
In the matter between:
GCWABE CONSULTING (PTY) LTD
Plaintiff
and
SOUTH
AFRICAN POICE SERVICE Defendant
JUDGMENT
JANSE VAN NIEUWENHUIZEN J:
[1] In the judgment handed down on 10 August 2022, the court declared the contract between the parties invalid.
[2] The only outstanding issue is the appropriate remedy consequent upon the aforesaid finding. Section 172(1)(b) of the Constitution enjoins the court to make any order that is just and equitable.
Just and equitable remedy
[3] The contract between the parties was concluded on 18 March 2013. Subsequent to the conclusion of the contract the plaintiff performed work in terms of the contract.
[4] In a letter dated 14 August 2013, the defendant informed the plaintiff that it was in breach of the contract in several respects and afforded the plaintiff 14 days to rectify the breach.
[5] The plaintiff did not, according to the defendant, rectify the breach and the contract was cancelled by the defendant on 4 November 2013.
[6) It is common cause between the parties that the plaintiff was duly paid for all the work it performed in terms of the contract.
[7] In Buffalo City Metropolitan Municipality v Asia Construction (Pty) Ltd 2019 (4) SA 331 CC, the Constitutional court considered a just and equitable remedy in circumstances where a contractor has performed in terms of a contract that was declared invalid.
[8] Having considered the facts of the matter the court held as follows at para (105]:
"..I therefore make an order declaring the Reeston contract invalid, but not setting it aside so as to preserve the rights to that the respondent might have been entitled. It should be noted that such an award preserves rights which have already accrued but does not permit a party to obtain further rights under the invalid contract."
[9] The facts in casu differ somewhat from the facts in Buffalo City. The plaintiff claims damages in the amount of R 50 858 579, 43 due to the defendant's breach alternatively repudiation of the contract. The amount represents the plaintiffs loss of income for the remaining period of the contract.
[10] Should the contract not be set aside, the plaintiffs claim will remain intact and will result in an undue benefit derived from a contract that has been declared invalid.
[11] In the result, I am of the view that a just and equitable remedy in the circumstances will be to set the contract aside.
COSTS
[12] Mr Mureriwa, counsel for the plaintiff, submitted that the plaintiff should not be mulcted with costs in circumstances where it is the innocent party. Mr Mureriwa contended that it is the officials in the employ of the defendant that failed to follow the prescribed procurement process and that the plaintiff acted in good faith in entering into the contract.
[13] The submission would have been convincing, if the plaintiff did not, notwithstanding the plea of invalidity, pursued the matter. The defendant was successful in its counterclaim and there is no reason why costs should not follow the cause.
ORDER
In the premises, I issue the following order:
1. The contract between the parties is set aside.
2. The plaintiff is ordered to pay the costs, which costs includes the costs of two counsel and the costs reserved on 10 August 2022.
N.
JANSE VAN NIEUWENHUIZEN
JUDGE
OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG DIVISION, PRETORIA
DATE HEARD PER COVID19 DIRECTIVES:
10 and 11 August 2022
DATE DELIVERED PER COVID19 DIRECTIVES:
17 August 2022
APPEARANCES
For the Plaintiff: Advocate I Mureriwa
Instructed by :
Baloyi Masango Incorporated
For the Defendant Adv
JL Van der Merwe SC
Adv J Janse van Rensburg
Instructed by : Soutie
van Rensburg Attorneys
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.