Download PDF

South Africa Judgment

South Gauteng High Court, Johannesburg

Grinaker LTA Rail Link Joint Venture v Absa Insurance Company Limited and Others (24110/2014) [2015] ZAGPJHC 302 (10 November 2015)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court held that strict compliance with the terms of the on-demand guarantee was required. The certificate provided by the applicant did not comply with the guarantee's requirements, as it failed to certify the opinion of the entity referred to as 'G-LTA' in the guarantee. The applicant's argument that 'G-LTA' referred to Grinaker-LTA Earthworks Engineering was raised only in reply and not in the founding affidavit, which is impermissible. The guarantee was clear and unambiguous, and substantial or equivalent compliance was not sufficient. Accordingly, the first respondent was entitled to refuse payment under the guarantee.

Court disposition

Application dismissed with costs, including costs of two counsel.

Orders

  • The application is dismissed.
  • The applicant is to pay the costs of the application, including the costs of employing two counsel.

02

Material facts

Parties

Grinaker-LTA Rail Link Joint Venture

Applicant Counsel: JP Daniels SC, S Bunn

Absa Insurance Company Limited

Respondent Counsel: I Green SC

Tshireletso Business Engineering (Pty) Ltd

Respondent

One Commercial Securities (Pty) Ltd

Respondent

Amounts and remedies

  • Guaranteed Amount: ZAR 3,864,827.84

03

Procedural history

  1. Posture

    Urgent Application / Application for Payment Under on Demand Guarantee

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that the abbreviation 'G-LTA' in the guarantee referred to Grinaker-LTA Earthworks Engineering, and that the certificate signed by its managing director constituted the required certification of opinion regarding breach by the subcontractor. The applicant contended that the guarantee did not require more than the certificate provided and that the demand was valid.
Respondent
The first respondent argued that the certificate did not comply with the guarantee's requirements, as it failed to certify the opinion of the correct entity ('G-LTA') as specified in the guarantee. The respondent maintained that strict compliance was required and that the applicant's interpretation was raised only in reply, which is impermissible. The respondent also initially raised a typographical error in the registration number but did not persist with this point.

05

Court’s reasoning

  1. 01

    OK Bazaars (1999) Ltd v Standard Bank of South Africa Ltd 2002 (3) SA 688 (SCA) at 697 para [25]

    Strict compliance with the terms of a performance guarantee is required; the issuing bank or guarantor must pay only if the demand and supporting documents conform exactly to the guarantee's requirements.

  2. 02

    Edward Owen Engineering Limited v Barclays Bank International Limited [1978] QB 159 (CA); [1978] 1 All ER 976

    A bank which gives a performance guarantee must honour that guarantee according to its terms, without investigating the underlying contractual position, except in cases of clear fraud.

  3. 03

    Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA) at para [20]

    The only basis upon which a bank can escape liability under a guarantee is proof of fraud on the part of the beneficiary.

  4. 04

    Riddle v Riddle 1956(2) SA 739 at 478

    It is impermissible for an applicant to make out a new case in reply; all allegations necessary to establish the cause of action must appear in the founding papers.

06

Ratio, limits and disposition

Ratio decidendi

The court held that strict compliance with the terms of the on-demand guarantee was required. The certificate provided by the applicant did not comply with the guarantee's requirements, as it failed to certify the opinion of the entity referred to as 'G-LTA' in the guarantee. The applicant's argument that 'G-LTA' referred to Grinaker-LTA Earthworks Engineering was raised only in reply and not in the founding affidavit, which is impermissible. The guarantee was clear and unambiguous, and substantial or equivalent compliance was not sufficient. Accordingly, the first respondent was entitled to refuse payment under the guarantee.

Obiter and limits

  • The court noted that the identity of 'G-LTA' was not established in the founding papers and that the abbreviation was not defined in the guarantee, leaving ambiguity as to which entity's opinion was required.
  • The court emphasized that the guarantee required no interpretation or clarification and that compliance must be literal and strict, not substantial or equivalent.

Court disposition

Application dismissed with costs, including costs of two counsel.

  • The application is dismissed.
  • The applicant is to pay the costs of the application, including the costs of employing two counsel.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Judgment

[2015] ZAGPJHC 302

REPUBLIC OF SOUTH

AFRICA

SOUTH

GAUTENG HIGH COURT JOHANNESBURG

CASE NO: 24110/2014

DATE: 10 NOVEMBER 2015

In the matter between:

GRINAKER-LTA

RAIL LINK JOINT VENTURE..............................................................Applicant

And

ABSA

INSURANCE COMPANY LIMITED.............................................................First Respondent

TSHIRELETSO BUSINESS ENGINEERING (PTY) LTD.................................Second Respondent

ONE COMMERCIAL SECURITIES (PTY) LTD..................................................Third Respondent

JUDGMENT

[1] In this application, the Applicant seeks an order directing the First Respondent to make payment to it of R3 864 827.84 under an "on-demand” construction guarantee. The Applicant is a joint-venture entity formed for the purposes of conducting certain construction works. The Second Respondent is a sub-contractor with whom the Applicant contracted to perform services in connection with the construction works. The furnishing of the guarantee was required in terms of the contract between the Second Respondent and the Applicant to secure the performance of the Second Respondent.

[2] The guarantee was procured by the Second Respondent on 20 December 2011. The following are relevant clauses of the performance guarantee:

1. It was issued by the Third Respondent on behalf of the First Respondent.

2. It was unconditional and irrevocable.

3. In it the First Respondent made the following undertaking:

“ 1. The Guarantor will

1.1 pay without delay to GRINAKER-LTA RAIL LINK JOINT VENTURE on the first written demand and without proof of any breach of contract by the Sub Contractor other than the certificate specified in 1.2 below, amounts not exceeding the following amounts:

THREE

MILLION EIGHT HUNDRED AND SIXTY FOUR THOUSAND EIGHT HUNDRED AND TWENTY SEVEN RAND AND EIGHTY FOUR CENTS (in words): R3 864 827.84 (in figures)( “the Guaranteed Amount”)

1.2 Make such payment/s to GRINAKER-LTA RAIL LINK JOINT VENTURE upon receipt by the Guarantor of a certificate signed by the Managing Director of Grinaker- LTA Earthworks Engineering certifying that the Sub Contractor, in the opinion of G-LTA, as at the date of issue of such certificate is in breach of its contractual obligations to GRINAKER-LTA RAIL LINK JOINT VENTURE under the Contract.

1.3 Make such payment/s to GRINAKER-LTA RAIL LINK JOINT VENTURE at an address designated by GRINAKER-LTA RAIL LINK JOINT VENTURE for this purpose.” (My emphasis)

[3] On 13 June 2014 the Applicant delivered:

1. a demand for payment under the guarantee;

2. the original guarantee; and

3. a certificate signed by the managing director of Grinaker-LTA Earthworks Engineering.

[4] This certificate has created the contention in this matter. It reads as follows:

“I, the undersigned,

Richard John Endell Evans

In my capacity as Managing Director of Grinaker-LTA Earthworks Engineering, do hereby certify that as at the date of signing hereof

Tshireletso Business Engineering (Pty) Limited (Tshireletso):

Registration number 2002/0074022/07

Is in breach of its contractual obligations to Grinaker-LTA Rail Link Joint Venture in terms of the Sub Contract agreement entered into between Grinaker-LTA Rail link Joint Venture and Tshireletso on or about 18 August 2011..."

[5] The First Respondent opposes the relief sought. It contends that the certificate does not comply with the requirements of the guarantee and that it is thus neither entitled nor obliged to make payment under the guarantee. In its answering affidavit it contends as follows in this regard:

1. that in terms of the guarantee it was required that the Managing Director of Grinaker-LTA Earthworks Engineering certify that in the opinion of the Applicant the Second Respondent was in breach of its contract;

2. that the certificate issued did not certify an opinion of the Applicant as to the breach of the Second Respondent but rather certified, as a fact, that such breach had occurred;

3. that the company registration number of the Second Respondent set out in the certificate was not correct in that it contained a typographical error (i.e. a repeated 2) which error rendered the demand fatally defective.

[6] Mr Green, on behalf of the First Respondent, did not persist with the second point relating to the registration number.

[7] In its replying affidavit, the Applicant contended that the First Respondent’s assertion as to whose opinion needed to be certified was incorrect. It alleged that the abbreviated name "G-LTA” used in the guarantee to refer to the entity whose opinion was to be certified, was meant to be a reference to Grinaker-LTA Earthworks Engineering and not to the Applicant. It pointed in this regard to the fact that the Applicant is only ever referred to in the guarantee as "Grinaker-LTA Rail Link Joint Venture" and stated that, accordingly, this reference could not have been intended to be a reference to the Applicant. This is the only allegation put forward in relation to why "G-LTA" is a reference to Grinaker-LTA Earthworks Engineering and not any other party. Reference to the guarantee shows that “G-LTA” is not defined. It could conceivably be a reference to the Applicant

(as was apparently assumed by the First Respondent) or Grinaker - LTA Earthworks Engineering or even a third entity.

[8] Mr Daniels, on behalf of the Applicant argued that the court should, on the aforegoing assertion in the replying affidavit, make the finding that the reference to

“G-LTA” in the guarantee is meant to be a reference to Grinaker LTA Earthworks Engineering. He argued that, on an interpretation of the

guarantee, the reference to “G-LTA" could only be understood to be a reference to Grinaker-LTA Earthworks Engineering.

He argued further that, once this was accepted, then the arguments in relation to the fact that “an opinion" was not

specifically referred to was semantic in that the statement of fact by the Managing Director of Grinaker-LTA Earthworks Engineering, in his capacity as such, constituted the required expression of the opinion of Grinaker-LTA Earthworks Engineering’s as to such fact.

[9] A finding that the reference to "G-LTA” in the guarantee is a reference to Grinaker-LTA Earthworks Engineering is thus the starting point of the argument on behalf of the Applicant. Without such a finding the case for the Applicant cannot succeed. I say this because, if “G-LTA” cannot be said, in this context, to be Grinaker-LTA Earthworks Engineering, then it follows that the certification by the Managing Director cannot be argued, on any basis, to be the “opinion of G-LTA".

[10] Mr Green, on behalf of the First Respondent, argued that this was not a finding that this court is called upon to make in this application. I am inclined to agree with this submission - on two bases:

2. secondly, because such a finding is irrelevant to the liability of the First Respondent to make payment under the guarantee in light of the requirement that a guarantee of the type in issue be strictly complied with.

[11] On the first basis - one would have expected the contention that the parties intended the abbreviation “G-LTA” be a reference to Grinaker-LTA Earthworks Engineering to have been made in the founding affidavit. However, the first time that the contention is made is in reply. There is no reason why the Applicant should be allowed to make this case in reply. Van Winsen J stated the general principle against making out a case in reply thus in Riddle v Riddle:[1]

“Undoubtedly, it is a general rule of our practice that all allegations necessary to establish the applicant’s cause of action must appear in the petition and/or the supporting affidavits and that the petitioner cannot cure a deficient case or fortify one, inadequately set forth, by introducing new matter in his replying affidavits, and that if he attempts to do so the offending paragraphs in the latter affidavits will be struck out. See for instance Coffee, Tea & Chocolate Co. Ltd. v Cape Trading Co., 1930 CPD 81 at p82; Victor v Victor 1938 WLD 16; Mauerberger v Mauerberger, 1948 (3) SA 731 (C) and Bayat and others v Hansa and Another 1955 (3) SA 547 at p553 (N)."

[12] In any event, and even were the case made out, the matter would still fall to be determined against the Applicant on the second basis, on the reasoning that follows.

[13] This Court is called upon to determine whether the First Respondent was entitled to refuse to make payment under the guarantee in light of the terms of the certificate in issue. The enquiry should not be elevated to a case about the interpretation of the guarantee. The guarantee is a written agreement. It is clear and unambiguous and capable of being complied with according to its tenor. It requires no interpretation or clarification as to what was required to achieve payment. There needed, in this context, to be no more than a reference in the certificate to the entity in question by the name used in the guarantee - i.e. “G-LTA”. Indeed it is not contemplated that any other name may be used.

[14] Strict compliance with the terms of the guarantee is required. Our courts have strictly applied the principle that a bank faced with a valid demand in respect of a performance guarantee is obliged to pay the beneficiary thereof without investigation of the underlying contractual position[2]. It is thus of no moment to the First Respondent who “G-LTA" is. This is not part of the field of its enquiry.

[15] Nugent JA, in OK Bazaars (1999) Ltd v Standard Bank of South Africa Ltd[3] had the following to say in relation to the obligations of an issuing bank that established a letter of credit (which is analogous to a guarantee of the type in issue herein[4]):

“...[the issuing bank’s] interest is confined to insuring that the documents that are presented conform with its client’s instructions (as reflected in the letter of credit) in which event the issuing bank is obliged to pay the beneficiary. If the presented documents do not conform with the terms of the letter of credit the issuing bank is neither obliged nor entitled to pay the beneficiary without its customer’s consent. The obligation of the issuing bank was expressed as follows in Midland Bank Limited v Seymour [1955] 2 Lloyds Rep 147 at 151:

There is, of course, no doubt that the bank has to comply strictly with the instructions that it is given by its customer. It is not for the bank to reason why. It is not for it to say: ‘This, that or the other does not seem to us very much to matter’. It is not for it to say: ‘What is on the bill of lading is just as good as what is in the letter of credit and means substantially the same thing’. All that is well established by authority. The bank must conform strictly to the instructions which it receives."

[16] In a similar vein, Lord Denning MR in Edward Owen Engineering Limited v

Barclays Bank International Limited[5] stated the following:

“A bank which gives a performance guarantee must honour that guarantee according to its terms. It is not concerned in the least with the relations between the supplier and the customer; nor the question whether the supplier has performed his contractual obligation or not; nor with the question whether the supplier is in default or not. The bank must pay according to its guarantee, on demand if so stipulated, without proof or conditions. The only exception is when there is a clear fraud of which the bank has notice."

[17] Similarly, in Lombard Insurance Co Limited v Landmark Holdings (Pty)

Ltd,[6] Navsa JA held:

“The guarantee by Lombard is not unlike irrevocable letters of credit issued by banks and used in international trade, the essential feature of which is the establishment of a contractual obligation on the part of a bank to pay the beneficiary (seller). ... The bank’s liability to the seller is to honour the credit. The bank undertakes to pay provided only that the conditions specified in the credit are met. The only basis upon which the bank can escape liability is proof of fraud on the part of the beneficiary...”

[18] The Applicant was thus neither entitled nor obliged to make the assumption or that "G-LTA" is a reference to Grinaker-LTA Earthworks Engineering nor was it obliged to enter in to an enquiry in relation to this aspect. It was necessary only that it establish, from the face of the certificate, that the entity whose opinion was being certified was the entity contemplated in the guarantee. The question is thus not whether Grinaker-LTA Earthworks Engineering is indeed the entity whose opinion is to be certified in terms of the guarantee but rather whether the certificate has been drawn on the basis that the required certification of opinion emerges therefrom. Accordingly, there is no basis for this court to enter into an enquiry relating to the intended identity of “G-LTA". The Applicant is simply not entitled to secure payment against a demand that is at odds with the strict and literal requirements of the guarantee (i.e. a certification of the opinion of an entity called “G-LTA’). Substantial or equivalent compliance (i.e. certification of the opinion of an entity that does not emerge from the certificate as being that that specified in the guarantee) is not permissible on the cases which I have referred to above.

[19] In the circumstances, the application must fail:

[20] I thus make the following order:

1. The application is dismissed.

2. The Applicant is to pay the costs of the application, which costs are to include the costs of employing two counsel.

DC FISHER

Acting Judge of the High Court APPEARANCES:

For the Applicant: Adv JP Daniels SC, together with S Bunn, instructed by Cliffe Dekker Hofmeyr Inc (Ref: Adine Abro/01962178; Tel 011 562 1009)

For the First Respondent Adv I Green SC, instructed by Edward Nathan Sonnenbergs Inc (Ref: A Meyerov; Tel: 011 269 7940)

DATE OF HEARING 9 October 2014

DATE OF JUDGMENT 10 November 2014

1. firstly, because a case was not made out that the reference to “G-LTA” in the guarantee was intended to be a reference to Grinaker-LTA Earthworks Engineering; and

' 1956(2) SA 739 at 478

[2] Guardrisk Insurance Company Ltd v Kentz (Pty) Ltd 2013 JDR 2727 (SCA) at pi5, para [28]

[3] 2002 (3) SA 688 at 697 para [25]

[4] Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA) at para [20]

[5] [1978] QB 159 (CA); [1978] 1 All ER 976 at 983B to D (all England Reports) and 171 A to B (QB)

[5] [1978] QB 159 (CA); [1978] 1 All ER 976 at 983B to D (all England Reports) and 171 A to

B (QB)

[6] supra at para [20]

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Guardrisk Insurance Company Ltd v Kentz (Pty) Ltd 2013 JDR 2727 (SCA) at p15, para [28]

Case cited

OK Bazaars (1999) Ltd v Standard Bank of South Africa Ltd 2002 (3) SA 688 (SCA) at 697 para [25]

Case cited

Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA) at para [20]

Case cited

Edward Owen Engineering Limited v Barclays Bank International Limited [1978] QB 159 (CA); [1978] 1 All ER 976

Case cited

Riddle v Riddle 1956(2) SA 739 at 478

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.