Group Five Construction (Pty) Ltd v Minister of Water Affairs and Forestry (379/2010) [2011] ZASCA 17 (14 March 2011)
The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.
- Citation
- [2011] ZASCA 17
- Parties
- Appellant: Group Five Construction (Pty) Limited; Respondent: Minister of Water Affairs and Forestry
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 14 March 2011
- Case Number
- 379/2010
- Procedural Posture
- Civil Appeal / Appeal From North Gauteng High Court
- Outcome
- Appeal dismissed with costs, including costs of two counsel.
- Judges
- Harms, Streicher, Brand, Shongwe, Theron
- Legal Topics
- Prescription Act, Building Contracts, Debt Due, Dispute Resolution Mechanism
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Group Five Construction (Pty) Limited
Appellant
Minister of Water Affairs and Forestry
Respondent
Procedural Posture
Civil Appeal / Appeal From North Gauteng High Court
Legal Issues
- 1 Whether the appellant's claims for additional payment under the building contract became 'due' upon giving written notice after the dispute review board's recommendation or only after completion of the works.
- 2 Whether the claims had prescribed in terms of section 12(1) of the Prescription Act 68 of 1969.
Ratio Decidendi
The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.
Court Disposition
Appeal dismissed with costs, including costs of two counsel.
Orders
- The appeal is dismissed with costs including costs of two counsel.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment