Group Five Construction (Pty) Ltd v Minister of Water Affairs and Forestry (379/2010) [2011] ZASCA 17 (14 March 2011)
- Citation
- [2011] ZASCA 17
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Supreme Court of Appeal
- Panel
- Harms, Streicher, Brand, Shongwe, Theron
- Case number
- 379/2010
More details
- Court
- Supreme Court of Appeal
- Panel
- Harms, Streicher, Brand, Shongwe, Theron
- Case number
- 379/2010
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.
Court disposition
Appeal dismissed with costs, including costs of two counsel.
Orders
- The appeal is dismissed with costs including costs of two counsel.
02
Material facts
Parties
Group Five Construction (Pty) Limited
Appellant Counsel: G D Harpur SCMinister of Water Affairs and Forestry
Respondent Counsel: R J Raath SC03
Procedural history
Posture
Civil Appeal / Appeal From North Gauteng High Court
04
Questions and positions
Legal issues
- 01
Whether the appellant's claims for additional payment under the building contract became 'due' upon giving written notice after the dispute review board's recommendation or only after completion of the works.
- 02
Whether the claims had prescribed in terms of section 12(1) of the Prescription Act 68 of 1969.
Party arguments
- Applicant
- The appellant argued that its claims for additional payment under the contract were based on estimates and represented advances, not complete claims. Therefore, the debts were not immediately due and prescription had not commenced. The appellant contended that the claims only became due after completion of the works as defined in the contract.
- Respondent
- The respondent submitted that the claims became due when the appellant gave written notice of its intention to refer the unresolved matters to court, following the dispute review board's recommendation. Accordingly, prescription commenced at that stage, and the claims had become prescribed by the time proceedings were instituted.
05
Court’s reasoning
Legal principles
- 01
Section 12(1) of the Prescription Act 68 of 1969
Prescription commences to run as soon as the debt is due, meaning when the creditor can demand performance from the debtor.
- 02
Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010)
Where a contract provides for a dispute resolution mechanism and written notice is required to refer a dispute to court, the claim becomes due upon giving such notice.
06
Ratio, limits and disposition
Ratio decidendi
The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.
Obiter and limits
- The court noted that the appellant's counsel made a valiant attempt to argue otherwise but missed the point regarding when the debt became due.
- The judgment of Southwood J in the court below was described as detailed and thorough, and the Supreme Court of Appeal found it unassailable.
Court disposition
Appeal dismissed with costs, including costs of two counsel.
- The appeal is dismissed with costs including costs of two counsel.
Source and reliance status
Supreme Court of Appeal
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Supreme Court of Appeal
Judgment
THE SUPREME COURT OF APPEAL OF
SOUTH AFRICA
JUDGMENT
Case no: 379/2010
In the matter between:
GROUP FIVE CONSTRUCTION (PTY) LIMITED ............................................Appellant
and
THE
MINISTER OF WATER AFFAIRS AND FORESTRY ..........................Respondent
Neutral citation: GROUP FIVE v MINISTER WATER AFFAIRS (379/10) [2011] ZASCA 17 (14 March 2011)
Coram: HARMS DP, STREICHER, BRAND, SHONGWE and THERON JJA
Heard: 1 MARCH 2011
Delivered: 14 MARCH 2011
SUMMARY: Building Contract – claims for additional payment or compensation – special plea of prescription
_______________
ORDER
On appeal from: North Gauteng High Court (Pretoria) (Southwood J sitting as court of first instance).
The appeal is dismissed with costs including costs of two counsel.
SHONGWE JA (HARMS DP, STREICHER, BRAND and THERON JJA concurring):
[1] The appellant, Group Five Construction (Pty) Limited, instituted a claim against the respondent, the Minister of Water Affairs and Forestry, for moneys allegedly due in terms of a contract for the construction of the Injaka dam and appurtenant works for the Sabie River Government Water Scheme. Four of the claims arose from claims submitted by the appellant in terms of clause 51 of the contract, which entitled the appellant to claim for additional payment or compensation in prescribed circumstances. The fifth claim, claim E, did not arise for adjudication.
[2] The respondent raised a special plea of prescription and the court below decided to hear this issue separately. The parties placed a list of agreed facts before the court, and led evidence. However, the validity of the special plea depended in the main on an interpretation of the rather complicated contract which had to be read with two amendments agreed to between the parties. These amendments affected clause 61 of the main contract and provided for a new dispute resolution mechanism of submitting disputes to a dispute review board, in lieu of mediation, which was obliged, during the course of the contract, to attempt to settle disputes that arose between the contractor and the employer pursuant to the rejection by the engineer of claims submitted.
[3] The amendment provided in summary that the board had to make recommendations to the parties. These became final and binding on the parties if they were accepted by them in writing. To the extent that a recommendation was not acceptable in writing by the parties, either party was entitled to refer the unresolved matter to court provided that the particular party had within 60 days, given written notice of its intention to do so. Otherwise the decision of the engineer was to become final and binding.
[4] Therefore the crisp issue between the parties was whether the appellant’s claims, which were the subject of this process,
became ‘due’ at the stage when the said written notice was given or whether these claims only became due after completion of the ‘works’ as defined in the contract (as contended by the appellant). The relevance of the issue is to be found in section 12(1) of the Prescription Act 68 of 1969, which provides that prescription commences ‘to run as soon as the debt is due’. It is common cause that if the appellant’s causes of action were ripe and complete when the notices were given these claims had clearly become prescribed.
[5] Southwood J, in a detailed and thorough judgment, reported as Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010), came to the conclusion that the claims indeed became prescribed. In spite of a valiant attempt by the appellant’s counsel to convince us otherwise, he missed the point in that he argued that the claims were based on an estimate and consequently represented an advance and not a complete claim ‘of which the debtor is under an obligation to perform immediately’. We are satisfied that Southwood J’s judgment is unassailable and that the argument does not warrant another judgment consisting of the same reasons albeit in different words.
[6] The appeal is dismissed with costs including costs of two counsel.
_____
J SHONGWE
JUDGE OF APPEAL
APPEARANCES:
For Appellant: G D Harpur SC
N D Lange
Instructed by:
Garlicke & Bousfield Inc
UMHLANGA
ROCKS
Claude Reid Inc
BLOEMFONTEIN
For Respondents: R J Raath SC
P M Mtshaulana SC
Instructed by: The State Attorney
PRETORIA
The State Attorney
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.