Download PDF

South Africa Judgment

Supreme Court of Appeal

Group Five Construction (Pty) Ltd v Minister of Water Affairs and Forestry (379/2010) [2011] ZASCA 17 (14 March 2011)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.

Court disposition

Appeal dismissed with costs, including costs of two counsel.

Orders

  • The appeal is dismissed with costs including costs of two counsel.

02

Material facts

Parties

Group Five Construction (Pty) Limited

Appellant Counsel: G D Harpur SC

Minister of Water Affairs and Forestry

Respondent Counsel: R J Raath SC

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From North Gauteng High Court

04

Questions and positions

Legal issues

Party arguments

Applicant
The appellant argued that its claims for additional payment under the contract were based on estimates and represented advances, not complete claims. Therefore, the debts were not immediately due and prescription had not commenced. The appellant contended that the claims only became due after completion of the works as defined in the contract.
Respondent
The respondent submitted that the claims became due when the appellant gave written notice of its intention to refer the unresolved matters to court, following the dispute review board's recommendation. Accordingly, prescription commenced at that stage, and the claims had become prescribed by the time proceedings were instituted.

05

Court’s reasoning

  1. 01

    Section 12(1) of the Prescription Act 68 of 1969

    Prescription commences to run as soon as the debt is due, meaning when the creditor can demand performance from the debtor.

  2. 02

    Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010)

    Where a contract provides for a dispute resolution mechanism and written notice is required to refer a dispute to court, the claim becomes due upon giving such notice.

06

Ratio, limits and disposition

Ratio decidendi

The Supreme Court of Appeal held that the appellant's claims for additional payment under the building contract became due when written notice was given to refer the unresolved matters to court, following the dispute review board's recommendation. This interpretation was based on the contract's dispute resolution mechanism and the Prescription Act. The court found that the claims were ripe and complete at the time the notices were given, and prescription commenced from that point. The appellant's argument that the claims were merely estimates and not immediately due was rejected. The court affirmed the reasoning of the lower court and concluded that the claims had prescribed.

Obiter and limits

  • The court noted that the appellant's counsel made a valiant attempt to argue otherwise but missed the point regarding when the debt became due.
  • The judgment of Southwood J in the court below was described as detailed and thorough, and the Supreme Court of Appeal found it unassailable.

Court disposition

Appeal dismissed with costs, including costs of two counsel.

  • The appeal is dismissed with costs including costs of two counsel.

Source and reliance status

Supreme Court of Appeal

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Supreme Court of Appeal

Judgment

[2011] ZASCA 17

THE SUPREME COURT OF APPEAL OF

SOUTH AFRICA

JUDGMENT

Case no: 379/2010

In the matter between:

GROUP FIVE CONSTRUCTION (PTY) LIMITED ............................................Appellant

and

THE

MINISTER OF WATER AFFAIRS AND FORESTRY ..........................Respondent

Neutral citation: GROUP FIVE v MINISTER WATER AFFAIRS (379/10) [2011] ZASCA 17 (14 March 2011)

Coram: HARMS DP, STREICHER, BRAND, SHONGWE and THERON JJA

Heard: 1 MARCH 2011

Delivered: 14 MARCH 2011

SUMMARY: Building Contract – claims for additional payment or compensation – special plea of prescription

_______________

ORDER

On appeal from: North Gauteng High Court (Pretoria) (Southwood J sitting as court of first instance).

The appeal is dismissed with costs including costs of two counsel.

SHONGWE JA (HARMS DP, STREICHER, BRAND and THERON JJA concurring):

[1] The appellant, Group Five Construction (Pty) Limited, instituted a claim against the respondent, the Minister of Water Affairs and Forestry, for moneys allegedly due in terms of a contract for the construction of the Injaka dam and appurtenant works for the Sabie River Government Water Scheme. Four of the claims arose from claims submitted by the appellant in terms of clause 51 of the contract, which entitled the appellant to claim for additional payment or compensation in prescribed circumstances. The fifth claim, claim E, did not arise for adjudication.

[2] The respondent raised a special plea of prescription and the court below decided to hear this issue separately. The parties placed a list of agreed facts before the court, and led evidence. However, the validity of the special plea depended in the main on an interpretation of the rather complicated contract which had to be read with two amendments agreed to between the parties. These amendments affected clause 61 of the main contract and provided for a new dispute resolution mechanism of submitting disputes to a dispute review board, in lieu of mediation, which was obliged, during the course of the contract, to attempt to settle disputes that arose between the contractor and the employer pursuant to the rejection by the engineer of claims submitted.

[3] The amendment provided in summary that the board had to make recommendations to the parties. These became final and binding on the parties if they were accepted by them in writing. To the extent that a recommendation was not acceptable in writing by the parties, either party was entitled to refer the unresolved matter to court provided that the particular party had within 60 days, given written notice of its intention to do so. Otherwise the decision of the engineer was to become final and binding.

[4] Therefore the crisp issue between the parties was whether the appellant’s claims, which were the subject of this process,

became ‘due’ at the stage when the said written notice was given or whether these claims only became due after completion of the ‘works’ as defined in the contract (as contended by the appellant). The relevance of the issue is to be found in section 12(1) of the Prescription Act 68 of 1969, which provides that prescription commences ‘to run as soon as the debt is due’. It is common cause that if the appellant’s causes of action were ripe and complete when the notices were given these claims had clearly become prescribed.

[5] Southwood J, in a detailed and thorough judgment, reported as Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010), came to the conclusion that the claims indeed became prescribed. In spite of a valiant attempt by the appellant’s counsel to convince us otherwise, he missed the point in that he argued that the claims were based on an estimate and consequently represented an advance and not a complete claim ‘of which the debtor is under an obligation to perform immediately’. We are satisfied that Southwood J’s judgment is unassailable and that the argument does not warrant another judgment consisting of the same reasons albeit in different words.

[6] The appeal is dismissed with costs including costs of two counsel.

_____

J SHONGWE

JUDGE OF APPEAL

APPEARANCES:

For Appellant: G D Harpur SC

N D Lange

Instructed by:

Garlicke & Bousfield Inc

UMHLANGA

ROCKS

Claude Reid Inc

BLOEMFONTEIN

For Respondents: R J Raath SC

P M Mtshaulana SC

Instructed by: The State Attorney

PRETORIA

The State Attorney

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010)

Case cited

Prescription Act 68 of 1969

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.