Download PDF

South Africa Judgment

Eastern Cape High Court, East London Local Court

Mbelani v Eastern Cape Development Corporation (491/16) [2017] ZAECELLC 2 (24 January 2017)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the plaintiff's particulars of claim were fundamentally defective, lacking necessary factual averments to sustain any of the claims advanced. The plaintiff failed to specify the manner of the alleged breach of contract, did not provide a factual basis for either contractual or delictual damages, and omitted particulars regarding the quantum of damages claimed. The technical argument advanced by the plaintiff regarding premature setting down was rejected, as Rule 23(1) only requires an opportunity to amend where the exception is based on vagueness and embarrassment, not where it is based on a failure to disclose a cause of action. The exception was accordingly upheld, but the court granted the plaintiff leave to amend the particulars of claim within 15 days, considering that outright dismissal would be unduly harsh.

Court disposition

Exception upheld; plaintiff granted leave to amend particulars of claim within 15 days; costs awarded to defendant.

Orders

  • The exception is upheld.
  • The plaintiff is granted leave to amend his particulars of claim within 15 days from the date of this order.
  • The plaintiff is ordered to pay the costs of the exception.

02

Material facts

Parties

Dalubuhle Mbelani

Plaintiff Counsel: Adv Ntila

Eastern Cape Development Corporation

Defendant Counsel: Mr S Rorke SC

Amounts and remedies

  • Remuneration Claimed for November, December and January: ZAR 171,044.5
  • Damages Claimed From Date of Suspension to Date: ZAR 2,000,000

03

Procedural history

  1. Posture

    Civil Procedure / Exception to Particulars of Claim

04

Questions and positions

Legal issues

Party arguments

Applicant
The plaintiff argued, through technical submissions, that the defendant had prematurely set the exception down for argument without affording the plaintiff an opportunity to remedy the defects as required by Rule 23(1). The plaintiff did not contest the substantive grounds of the exception and relied solely on procedural objections.
Respondent
The defendant contended that the particulars of claim lacked necessary factual averments to sustain any claim, failed to specify the manner of the alleged breach, conflated contractual and delictual damages, and did not provide particulars regarding the quantum of damages as required by Rule 18(10). The defendant argued that these deficiencies rendered it impossible to discern the case to be pleaded to.

05

Court’s reasoning

  1. 01

    Rule 18(10) of the Uniform Rules of Court

    A pleading must contain sufficient particularity to enable the opposing party to know the case it must meet and to plead accordingly.

  2. 02

    Rule 23(1) of the Uniform Rules of Court

    Exceptions may be taken where a pleading lacks averments necessary to sustain a cause of action, and the court may uphold such exceptions if the pleading is fundamentally defective.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the plaintiff's particulars of claim were fundamentally defective, lacking necessary factual averments to sustain any of the claims advanced. The plaintiff failed to specify the manner of the alleged breach of contract, did not provide a factual basis for either contractual or delictual damages, and omitted particulars regarding the quantum of damages claimed. The technical argument advanced by the plaintiff regarding premature setting down was rejected, as Rule 23(1) only requires an opportunity to amend where the exception is based on vagueness and embarrassment, not where it is based on a failure to disclose a cause of action. The exception was accordingly upheld, but the court granted the plaintiff leave to amend the particulars of claim within 15 days, considering that outright dismissal would be unduly harsh.

Obiter and limits

  • The court noted that the plaintiff appeared to conflate contractual and delictual damages without providing a factual basis for either.
  • The court observed that the defendant's request for dismissal of the claim was conceded to be unduly harsh, and leave to amend was more appropriate.

Court disposition

Exception upheld; plaintiff granted leave to amend particulars of claim within 15 days; costs awarded to defendant.

  • The exception is upheld.
  • The plaintiff is granted leave to amend his particulars of claim within 15 days from the date of this order.
  • The plaintiff is ordered to pay the costs of the exception.

Source and reliance status

Eastern Cape High Court, East London Local Court

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Eastern Cape High Court, East London Local Court

Judgment

[2017] ZAECELLC 2

IN THE HIGH COURT OF

SOUTH AFRICA

EASTERN CAPE DIVISION – EAST LONDON

Case no: 491/16

ECD: 1191/16

Case Heard: 06/12/2016

Date Delivered: 24/01/2017

In the matter between:

DALUBUHLE

MBELANI

PLAINITFF

and

EASTERN

CAPE DEVELOPMENT CORPORATION DEFENDANT

JUDGMENT

SMITH J:

[1] The defendant filed an exception to the plaintiff’s particulars of claim on the following grounds:

(a) in paragraph 7(ii) thereof the plaintiff alleges that the defendant has breached the terms of the agreement, but fails to provide any particularity regarding the manner of the alleged breach;

(b) the plaintiff has failed to provide sufficient particularity regarding the nexus between the alleged breach and the damages claimed. There is also no particularity regarding the quantum of damages as required by Rule 18(10) of the Uniform Rules of Court; and

(c) the plaintiff has failed to provide a proper factual basis for his prayer for a “Verdict on suspension within 15 (fifteen) days alternatively re-instatement of the plaintiff”.

[2] After the defendant filed its exception on 16 May 2016, the plaintiff gave notice of his intention to amend his particulars of claim. The defendant then filed an objection to the proposed amendment on the ground that the particulars of claim would remain excipiable. The plaintiff did not thereafter seek leave to amend in terms of Rule 28(4), and the exception must accordingly be adjudicated on the particulars of claim in its original form.

[3] The plaintiff’s cause of action was founded on the alleged breach of a contract of employment in terms of which he was employed as the defendant’s Company Secretary. He alleges that the defendant breached the agreement by failing to:

(i) remunerate the plaintiff for the months of November, December and January 2015, respectively; and

(ii) comply with “30 days suspension period as stipulated in the contract of employment”.

[4] He avers (in paragraph 8) that as a result of the breach the plaintiff suffered “loss of income” and “damages”. No further particularity is provided regarding the manner of the alleged breach, or how the claims in respect of loss of income and damages are calculated. It is only in the prayer section of the claim where the following is stated:

“ (a) payment of an amount of R171 044. 50 (one hundred and seventy one thousand and forty four rand and fifty cents) being the

remuneration for the months of November, December and January underpayment, respectively;”

“(c) Verdict on suspension within 15 (fifteen) days, alternatively instatement of the plaintiff”; and

“d) Payment of the mount of R2 000 000.00 (two million rands) being damages suffered by the plaintiff from the date of suspension to date”.

[5] It must have been abundantly clear from the foregoing that the particulars of claim lack the necessary factual averments to sustain

any of the plaintiff’s claims, and it is consequently fundamentally defective.

[6] Mr Rorke SC, who appeared on behalf of the defendant, correctly argued that the plaintiff appeared to have conflated the nature of contractual and delictual damages; has in the event failed to provide a factual basis for his claim in either respect; has merely alleged a breach without providing any particularity as to the manner in which the defendant is alleged to have breached the contract; and has not provided any particulars regarding either the amount claimed for loss of earnings or damages, as required by Rule 18(10). It is consequently virtually impossible for the defendant to discern what case it is required to plead to.

[7] Unsurprisingly, Mr Ntila, who appeared for the plaintiff, was unable to contest the defendant’s contentions in this regard, and has instead resorted to a technical argument, namely that the defendant has prematurely set the matter down for argument without providing the plaintiff an opportunity to remedy the defects as required by Rule 23(1). There is of course no merit in that argument since the Rule clearly states that it is only where a party takes an exception that a pleading is vague and embarrassing that he or she must allow the opponent to remove the cause of complainant. The defendant’s exception is based on the ground that the particulars of claim lack averments necessary to sustain a cause of action. The exception must accordingly be upheld.

[8] Although the defendant has prayed for the exception to be upheld and the plaintiff’s claim to be dismissed, Mr Rorke has conceded that such an order would be unduly harsh.

[9] In the result the exception is upheld, with costs, and the plaintiff is granted leave to amend his particulars of claim within a period of 15 days from the date of this order.

_____

J.E

SMITH

JUDGE

OF THE HIGH COURT

Appearances

Counsel for the Defendant : Mr S Rorke SC

Attorney for the Defendant : Wesley Pretorius & Associates

Ground Floor

Pilot Mill House

The Quarry, Selborne

East London

Counsel for the Plaintiff : Adv Ntila

Attorney for the Plaintiff : Mtabela Attorneys & Associates

c/o Boboptyana & Compant

13 King Street

Date Heard

: 6 December 2016

Date Delivered : 24 January 2017

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Uniform Rules of Court, Rule 18(10)

Legislation

Legislation referenced in the available case record.

Uniform Rules of Court, Rule 23(1)

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.