Mbelani v Eastern Cape Development Corporation (491/16) [2017] ZAECELLC 2 (24 January 2017)
- Citation
- [2017] ZAECELLC 2
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- Eastern Cape High Court, East London Local Court
- Panel
- J.E Smith
- Case number
- 491/16
More details
- Court
- Eastern Cape High Court, East London Local Court
- Panel
- J.E Smith
- Case number
- 491/16
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the plaintiff's particulars of claim were fundamentally defective, lacking necessary factual averments to sustain any of the claims advanced. The plaintiff failed to specify the manner of the alleged breach of contract, did not provide a factual basis for either contractual or delictual damages, and omitted particulars regarding the quantum of damages claimed. The technical argument advanced by the plaintiff regarding premature setting down was rejected, as Rule 23(1) only requires an opportunity to amend where the exception is based on vagueness and embarrassment, not where it is based on a failure to disclose a cause of action. The exception was accordingly upheld, but the court granted the plaintiff leave to amend the particulars of claim within 15 days, considering that outright dismissal would be unduly harsh.
Court disposition
Exception upheld; plaintiff granted leave to amend particulars of claim within 15 days; costs awarded to defendant.
Orders
- The exception is upheld.
- The plaintiff is granted leave to amend his particulars of claim within 15 days from the date of this order.
- The plaintiff is ordered to pay the costs of the exception.
02
Material facts
Parties
Dalubuhle Mbelani
Plaintiff Counsel: Adv NtilaEastern Cape Development Corporation
Defendant Counsel: Mr S Rorke SCAmounts and remedies
- Remuneration Claimed for November, December and January: ZAR 171,044.5
- Damages Claimed From Date of Suspension to Date: ZAR 2,000,000
03
Procedural history
Posture
Civil Procedure / Exception to Particulars of Claim
04
Questions and positions
Legal issues
- 01
Whether the plaintiff's particulars of claim disclose sufficient factual averments to sustain a cause of action.
- 02
Whether the plaintiff has provided adequate particularity regarding the alleged breach and the quantum of damages claimed.
- 03
Whether the defendant's exception should be upheld and the plaintiff's claim dismissed or amended.
Party arguments
- Applicant
- The plaintiff argued, through technical submissions, that the defendant had prematurely set the exception down for argument without affording the plaintiff an opportunity to remedy the defects as required by Rule 23(1). The plaintiff did not contest the substantive grounds of the exception and relied solely on procedural objections.
- Respondent
- The defendant contended that the particulars of claim lacked necessary factual averments to sustain any claim, failed to specify the manner of the alleged breach, conflated contractual and delictual damages, and did not provide particulars regarding the quantum of damages as required by Rule 18(10). The defendant argued that these deficiencies rendered it impossible to discern the case to be pleaded to.
05
Court’s reasoning
Legal principles
- 01
Rule 18(10) of the Uniform Rules of Court
A pleading must contain sufficient particularity to enable the opposing party to know the case it must meet and to plead accordingly.
- 02
Rule 23(1) of the Uniform Rules of Court
Exceptions may be taken where a pleading lacks averments necessary to sustain a cause of action, and the court may uphold such exceptions if the pleading is fundamentally defective.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the plaintiff's particulars of claim were fundamentally defective, lacking necessary factual averments to sustain any of the claims advanced. The plaintiff failed to specify the manner of the alleged breach of contract, did not provide a factual basis for either contractual or delictual damages, and omitted particulars regarding the quantum of damages claimed. The technical argument advanced by the plaintiff regarding premature setting down was rejected, as Rule 23(1) only requires an opportunity to amend where the exception is based on vagueness and embarrassment, not where it is based on a failure to disclose a cause of action. The exception was accordingly upheld, but the court granted the plaintiff leave to amend the particulars of claim within 15 days, considering that outright dismissal would be unduly harsh.
Obiter and limits
- The court noted that the plaintiff appeared to conflate contractual and delictual damages without providing a factual basis for either.
- The court observed that the defendant's request for dismissal of the claim was conceded to be unduly harsh, and leave to amend was more appropriate.
Court disposition
Exception upheld; plaintiff granted leave to amend particulars of claim within 15 days; costs awarded to defendant.
- The exception is upheld.
- The plaintiff is granted leave to amend his particulars of claim within 15 days from the date of this order.
- The plaintiff is ordered to pay the costs of the exception.
Source and reliance status
Eastern Cape High Court, East London Local Court
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Eastern Cape High Court, East London Local Court
Judgment
IN THE HIGH COURT OF
SOUTH AFRICA
EASTERN CAPE DIVISION – EAST LONDON
Case no: 491/16
ECD: 1191/16
Case Heard: 06/12/2016
Date Delivered: 24/01/2017
In the matter between:
DALUBUHLE
MBELANI
PLAINITFF
and
EASTERN
CAPE DEVELOPMENT CORPORATION DEFENDANT
JUDGMENT
SMITH J:
[1] The defendant filed an exception to the plaintiff’s particulars of claim on the following grounds:
(a) in paragraph 7(ii) thereof the plaintiff alleges that the defendant has breached the terms of the agreement, but fails to provide any particularity regarding the manner of the alleged breach;
(b) the plaintiff has failed to provide sufficient particularity regarding the nexus between the alleged breach and the damages claimed. There is also no particularity regarding the quantum of damages as required by Rule 18(10) of the Uniform Rules of Court; and
(c) the plaintiff has failed to provide a proper factual basis for his prayer for a “Verdict on suspension within 15 (fifteen) days alternatively re-instatement of the plaintiff”.
[2] After the defendant filed its exception on 16 May 2016, the plaintiff gave notice of his intention to amend his particulars of claim. The defendant then filed an objection to the proposed amendment on the ground that the particulars of claim would remain excipiable. The plaintiff did not thereafter seek leave to amend in terms of Rule 28(4), and the exception must accordingly be adjudicated on the particulars of claim in its original form.
[3] The plaintiff’s cause of action was founded on the alleged breach of a contract of employment in terms of which he was employed as the defendant’s Company Secretary. He alleges that the defendant breached the agreement by failing to:
(i) remunerate the plaintiff for the months of November, December and January 2015, respectively; and
(ii) comply with “30 days suspension period as stipulated in the contract of employment”.
[4] He avers (in paragraph 8) that as a result of the breach the plaintiff suffered “loss of income” and “damages”. No further particularity is provided regarding the manner of the alleged breach, or how the claims in respect of loss of income and damages are calculated. It is only in the prayer section of the claim where the following is stated:
“ (a) payment of an amount of R171 044. 50 (one hundred and seventy one thousand and forty four rand and fifty cents) being the
remuneration for the months of November, December and January underpayment, respectively;”
“(c) Verdict on suspension within 15 (fifteen) days, alternatively instatement of the plaintiff”; and
“d) Payment of the mount of R2 000 000.00 (two million rands) being damages suffered by the plaintiff from the date of suspension to date”.
[5] It must have been abundantly clear from the foregoing that the particulars of claim lack the necessary factual averments to sustain
any of the plaintiff’s claims, and it is consequently fundamentally defective.
[6] Mr Rorke SC, who appeared on behalf of the defendant, correctly argued that the plaintiff appeared to have conflated the nature of contractual and delictual damages; has in the event failed to provide a factual basis for his claim in either respect; has merely alleged a breach without providing any particularity as to the manner in which the defendant is alleged to have breached the contract; and has not provided any particulars regarding either the amount claimed for loss of earnings or damages, as required by Rule 18(10). It is consequently virtually impossible for the defendant to discern what case it is required to plead to.
[7] Unsurprisingly, Mr Ntila, who appeared for the plaintiff, was unable to contest the defendant’s contentions in this regard, and has instead resorted to a technical argument, namely that the defendant has prematurely set the matter down for argument without providing the plaintiff an opportunity to remedy the defects as required by Rule 23(1). There is of course no merit in that argument since the Rule clearly states that it is only where a party takes an exception that a pleading is vague and embarrassing that he or she must allow the opponent to remove the cause of complainant. The defendant’s exception is based on the ground that the particulars of claim lack averments necessary to sustain a cause of action. The exception must accordingly be upheld.
[8] Although the defendant has prayed for the exception to be upheld and the plaintiff’s claim to be dismissed, Mr Rorke has conceded that such an order would be unduly harsh.
[9] In the result the exception is upheld, with costs, and the plaintiff is granted leave to amend his particulars of claim within a period of 15 days from the date of this order.
_____
J.E
SMITH
JUDGE
OF THE HIGH COURT
Appearances
Counsel for the Defendant : Mr S Rorke SC
Attorney for the Defendant : Wesley Pretorius & Associates
Ground Floor
Pilot Mill House
The Quarry, Selborne
East London
Counsel for the Plaintiff : Adv Ntila
Attorney for the Plaintiff : Mtabela Attorneys & Associates
c/o Boboptyana & Compant
13 King Street
Date Heard
: 6 December 2016
Date Delivered : 24 January 2017
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.