Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Niemand v Hollard Insurance Company Limited (13691/2021) [2024] ZAGPPHC 1203 (22 November 2024)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The appellant's liability arises from the Deed of Indemnity and Suretyship, which obliges him to pay the respondent on demand any amount paid under the guarantee, irrespective of the underlying contract's status or the appellant's admission of liability. The advance payment guarantee is a conditional bond, but the respondent received a written demand stating breach and termination of the subcontract, and Wameschsi was under liquidation. These facts were not disputed. The formalities required by the guarantee presume completion of the contract, which did not occur. The respondent acted appropriately in honouring both guarantees. The appellant failed to demonstrate reasonable prospects of success or compelling reasons for leave to appeal. Accordingly, the application for leave to appeal is dismissed with costs.

Court disposition

Application for leave to appeal dismissed with costs, including counsel's fees.

Orders

  • The application for leave to appeal is dismissed with costs inclusive of counsel's fees.

02

Material facts

Parties

Lucas Jurie Niemand

Appellant Counsel: Adv. APJ Els S.C

The Hollard Insurance Company Limited

Respondent Counsel: Adv. K Mitchell

Amounts and remedies

  • Advance Payment Guarantee Amount: ZAR 6,500,000
  • Performance Guarantee Amount: ZAR 3,505,138.9

03

Procedural history

  1. Posture

    Leave to Appeal / Application for Leave to Appeal to the Supreme Court of Appeal or Full Bench, Following Judgment and Order Delivered on 10 April 2024.

04

Questions and positions

Legal issues

Party arguments

Applicant
The appellant contends that the guarantees issued by the respondent were subject to specific conditions which were not fulfilled. He argues that the respondent failed to demonstrate compliance with these conditions in its founding affidavit, and therefore was not obliged to pay under the guarantee. Consequently, the appellant asserts he cannot be held liable for payments made by the respondent to the contractor. He relies on the distinction between conditional and on-demand guarantees, referencing Guard Risk Insurance Co Ltd v Kentz (Pty) Ltd and Minister of Transport and Public Works, Western Cape & Another v Zanbuild Construction (Pty) Ltd & another. The appellant submits that there are reasonable prospects of success on appeal or other compelling reasons for leave to be granted.
Respondent
The respondent submits that the appellant's liability arises from the Deed of Indemnity and Suretyship, which is independent of the underlying contract. The indemnity obliges the appellant to pay on demand any amount the respondent is called upon to pay under the guarantee, regardless of the validity of the claim or the appellant's admission thereof. The respondent argues that upon receiving a written demand stating breach and termination of the subcontract, and with Wameschsi under liquidation, it was obligated to honour both the advance payment and performance guarantees. The respondent maintains that the formalities required by the guarantee presume the contract would be completed, which is not the case here, and thus compliance with those formalities is not a bar to payment.

05

Court’s reasoning

  1. 01

    Section 17(1)(a)(i) and (ii) of the Superior Courts Act 10 of 2013

    Leave to appeal should be granted if there are reasonable prospects of success or compelling reasons for the appeal to be heard.

  2. 02

    S v Smith 2012(1) SACR 567 (SCA) [2011] ZASCA 15

    The test for reasonable prospects of success requires a dispassionate decision that a court of appeal could reasonably arrive at a different conclusion, and prospects must be realistic, not remote.

  3. 03

    Guard Risk Insurance Co. Ltd v Kentz (Pty) Ltd (94/2013) [2013] ZASC 182; Minister of Transport and Public Works, Western Cape & Another v Zanbuild Construction (Pty) Ltd & another 2011(5) SA 528 (SCA)

    A conditional bond requires compliance with specified conditions for payment, whereas an on-demand bond requires only a demand stated to be on the basis of the event specified in the bond.

06

Ratio, limits and disposition

Ratio decidendi

The appellant's liability arises from the Deed of Indemnity and Suretyship, which obliges him to pay the respondent on demand any amount paid under the guarantee, irrespective of the underlying contract's status or the appellant's admission of liability. The advance payment guarantee is a conditional bond, but the respondent received a written demand stating breach and termination of the subcontract, and Wameschsi was under liquidation. These facts were not disputed. The formalities required by the guarantee presume completion of the contract, which did not occur. The respondent acted appropriately in honouring both guarantees. The appellant failed to demonstrate reasonable prospects of success or compelling reasons for leave to appeal. Accordingly, the application for leave to appeal is dismissed with costs.

Obiter and limits

  • The distinction between conditional and on-demand guarantees is material, but in this case, the indemnity operates independently of the underlying contract.
  • Formalities in the guarantee presume the contract's completion, which is not applicable where the contract has been terminated and the subcontractor is in liquidation.
  • The court was not referred to any particular circumstances that would constitute compelling reasons for granting leave to appeal.

Court disposition

Application for leave to appeal dismissed with costs, including counsel's fees.

  • The application for leave to appeal is dismissed with costs inclusive of counsel's fees.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2024] ZAGPPHC 1203

IN THE HIGH COURT OF

SOUTH AFRICA

GAUTENG DIVISION,

PRETORIA

Case No: 13691/2021

(1) REPORTABLE: NO

(2) OF INTREST TO OTHER JUDGES: NO

NKOSI AJ DATE: 22 NOVEMBER 2024

In the matter between:

NIEMAND,

LUCAS JURIE Appellant and

THE

HOLLARD INSURANCE COMPANY LIMITED Respondent In re:

THE

HOLLARD INSURANCE COMPANY LIMITED Applicant and

WAMESCHSI GROUP (PTY) LTD First Respondent NIEMAND,

LUCAS JURIE Second Respondent

Delivery: - This judgement was delivered electronically by means of email to the legal representatives of the parties and uploaded on Case Lines. The judgement is deemed to be delivered on the 22nd November 2024.

JUDGEMENT

NKOSI AJ.

[1] This is an application for leave to appeal to the Supreme Court of Appeal, alternatively to a full bench of this division, against the whole of the judgment and order of this Court delivered on 10 April 2024. The application is opposed.

[2] The application is premised on the provisions of Section 17(1)(a)(i) and (ii) of the Superior Courts Act 10 of 2013. It is submitted by the appellant that the application has reasonable prospects of success and that there are other compelling reasons why the appeal should be heard.

[3] The parties are ad idem concerning the applicable test for this application to succeed. Should there be prospects of success on appeal or if there are

compelling reasons for the appeal to be heard, leave to appeal should be granted. The appellant relied on the ratio in Ramakatsa v African National Congress and another[1] in his submission regarding the applicable test.

[4] In Air Chefs SOC Limited v The Public Protector of Republic of South Africa and Others[2], Adams J noted that the ratio in Ramakatsa simply followed S v Smith[3], and I agree. In S v Smith the Court held

“What the test of reasonable prospects of success postulates is a dispassionate decision, based on the facts and the law, that a court of appeal could reasonably arrive at a conclusion different to that of the trial court. In order to succeed, therefore, the appellant must convince this court on proper grounds that he has prospects of success on appeal and that those prospects are not remote but have a realistic chance of succeeding. More is required to be established than that there is a mere possibility of success, that the case is arguable on appeal or that the case cannot be categorized as hopeless. There must, in other words, be a sound, rational basis for the conclusion that there are prospects of success on appeal.”

[5] It is prudent at this stage to outline the factual background to this appeal before moving to deal with the grounds of appeal and the legal principles relevant thereto.

[6] It is common cause that the appellant’s indebtedness to the respondent emanates from a Deed of Indemnity and Suretyship (“the Indemnity”) which he executed in favor of the respondent. In terms of the Indemnity, the appellant bound himself as a co-principal debtor, in solidum, for the due payment by the first respondent[4] in the main application (“Wameschsi”) to the respondent herein, of all and any amounts which the respondent is called upon to pay under the Guarantee.

[7] The appellant also undertook to pay the respondent on demand any sum or sums of money which the respondent may be called upon to pay under the demand in terms of the guarantee whether or not the respondent shall, at such date, have made such payment, and whether or not Wameschsi or the appellant admits the validity of such claims against the respondent.

[8] It is further common cause that on or about 09 July 2020 and 26 June 2019, the respondent issued guarantees for the amount of R6, 500, 000.00 (Six million five hundred thousand rand) and R3, 505, 138.90 (Three million five hundred and five thousand one hundred and thirty-eight rand and ninety cents) respectively, at the request of Wameschsi.

[9] The nub of the disagreement in this application is the appellant’s contention that the guarantees were subject to specific conditions that had to be fulfilled. Further, that the compliance with these conditions had to be demonstrated in the founding affidavit in the main application. He submitted that the respondent failed to observe and comply with the conditions. He further contends that the respondent failed to demonstrate in its founding affidavit that it complied.

[10] The appellant mentioned in his heads of argument the conditions of the guarantee he refers to and states the following:

“… hereby irrevocably undertakes to pay you the Contractor, any sum or sums not exceeding in total the amount of R6 500 000.00 …(“the guaranteed amount”) upon receipt by the guarantor of your demand in writing which you may make if:

1.1 the Subcontractor has breached the subcontract or an event entitling

the Contractor to terminate the Subcontract has occurred resulting in the cancellation of the Subcontract; and

1.2 the Subcontractor has failed to repay the advance payment in

accordance with the conditions of the Subcontract.

2. This guarantee shall become effective upon receipt of the advance payment or any portion thereof by the Subcontractor in terms of the Subcontract. Such guaranteed amount shall be reduced by the amounts of the Advance Payment repaid to the Contractor or as deducted from payment certificates from time to time.

3. Any demand for payment must:

3.1 contain your signature(s) which must be authenticated by your bankers or by a notary public; and

3.2 have attached to it all payment certificates together with all recovery statements issued to the Subcontractor in terms of and in consequence of the Subcontract; and

3.3 the authenticated demand and certificates must be received by us at this office on or before the Expiry Date of the guarantee.”

[11] The above conditions concern the Advance Payment guarantee of R6, 500, 000.00. The other guarantee for R3, 505, 138.90 is a Performance Guarantee and does not have such conditions.

[12] It was further submitted that the contractor could not submit a demand for payment without complying with these specific conditions already mentioned above[5], and that the respondent was not obligated to pay. Consequently, the appellant cannot be held liable for payment made to the contractor by the respondent.

[13] The appellant referred court to the decision in Guard Risk Insurance Company Ltd v Kentz (Pty) Ltd[6] wherein Theron JA (as she was then), in dealing with the difference between the two types of guarantees, quoted from the case of Minister of Transport and Public Works, Western Cape and Another v Zanbuild Construction (Pty) Ltd and Another[7] wherein Brand JA said:

“…. a claimant under a conditional bond is required at least to allege and – depending on the terms of the bond – sometimes also to establish liability on the part of the contractor for the same amount. An ‘on demand’ bond, also referred to as a ‘call bond’, on the other hand, requires no allegation of liability on the part of the contractor under the construction contracts. All that is required for payment is a demand by the claimant, stated to be on the basis of the event specified in the bond”.

[14] It is clear from the wording of the Advance Payment Guarantee that it is a conditional bond and the compliance thereof is subject to the terms of the conditions. However, that is not the case with the Performance Guarantee. The stark facts which militate against appellant’s submission and the prospects of success on appeal are: -

14.1 the applicant’s liability to the respondent emanates from the

Indemnity which does not depend on the underlying contract. The applicant indemnified and kept the respondent indemnified and held harmless from and against all and any claim, losses, demands, liabilities, costs and expenses of whatsoever nature;

14.2 further and in terms of the Indemnity, the applicant undertook to pay the respondent on demand (my emphasis) any money the respondent may be called upon to pay under the Guarantee whether or not the applicant admits the validity of such claims against the respondent under the Guarantee. (my emphasis)

[15] I therefore do not agree with appellant’s contention that the respondent was not obliged to pay because the terms of the Advance Performance Guarantee were not met.

[16] The Advance Payment Guarantee further provides for the payment of the amount of R6, 500, 000.00 upon receipt by the respondent of a demand in writing under the circumstances where:

(i) the Subcontractor (Wameschi) has breached the subcontract or an event entitling the Contractor to terminate the Subcontract has occurred resulting in the cancellation of the Subcontract…” (my emphasis).

[17] The respondent received a written demand[8] from the contractor which mentioned that Wameschi was in breach of the underlying contract and further that it was under liquidation.

Wameschi was eventually placed under final winding up[9]. These facts were not disputed by the appellant. It was argued by the respondent that having received a written demand under these

circumstances it was obligated to honor the Advance Payment Guarantee and the Performance Guarantee. I am inclined to agree with the submission by the respondent more so that, in addition, the written demand also declares that the contract has been terminated,

therefore, the respondent cannot refuse to pay.

[18] In my view the other formalities contained in the guarantee which require that the signature should be authenticated, that all payment certificates together with all recovery statements should be attached to the demand and that the authenticated demand and certificates must be received by appellant, presume that the contract would be carried to its finality which is not the case herein.

[19] I am persuaded that the respondent acted appropriately by honoring the Advance Payment Guarantee and the Performance Guarantee because the prevailing circumstances entitled the contractor to invoke the provisions of the Advance Payment Guarantee and to cancel the agreement.

[20] Having regard to these prevailing circumstances and the findings I already made, I am of the view that the prospects of success, if any, are not good on appeal; additionally, the court was not referred to a particular set of circumstances to demonstrate that there are compelling reasons why the appeal should be heard.

[21] I therefore make the following order:

(i) The application for leave to appeal is dismissed with costs inclusive Counsel’s fees.

NKOSI AJ

ACTING JUDGE OF THE

HIGH COURT

Date of Hearing : 4 November 2024

Date Delivered : 22 November 2024

Appearances:

For the Appellant: Email: Adv. APJ Els S.C Instructed by; Eugene Beyers Attorneys e.beyersproks@gmail.com For the Respondent: Email: Adv. K Mitchell Instructed by; Moll Quibell and Associates daniel@mqlaw.co.za; zak@mqlaw.co.za; and fellon@mqlaw.co.za

This Judgment has been delivered by uploading it to the Case Lines digital data base of Gauteng Division, Pretoria and by email to the attorneys of record of the parties. The deemed date for the delivery is 22 November 2024.

[1] Ramakatsa and others v African National Congress and another (724/2019) [2021] ZASCA 31 (31 March 2021) at para 10

[2] Case No. (31083/2020) [2024] ZAGPJHC unreported (heard on 29 February 2024) at para 7

[3] S v Smith 2012(1) SACR 567 (SCA) [2011] ZASCA 15 at para 7

[4] WAMESCHSI GROUP (PTY) LTD, which is not part of these proceedings. The application for leave to appeal concerns Niemand and Hollard.

[4] WAMESCHSI GROUP (PTY) LTD, which is not part of these proceedings. The application for leave to appeal concerns

Niemand and Hollard.

[5] Para 10 supra

[6] Guard Risk Insurance Co. Ltd v Kentz (Pty) Ltd (94/2013) [2013] ZASC 182: [2014] IALLSA 307 (SCA) (29 November 2013) at para 10

[7] Minister of Transport and Public Works, Western Cape & Another v Zanbuild Construction (Pty) Ltd & another 2011(5) SA 528 (SCA) para 13.

[8] Caseline 006 - 60

[9] Caseline 006 – 24, Court order by Swanepoel AJ (as he then was)

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Ramakatsa and others v African National Congress and another (724/2019) [2021] ZASCA 31 (31 March 2021)

Case cited

Air Chefs SOC Limited v The Public Protector of Republic of South Africa and Others (31083/2020) [2024] ZAGPJHC unreported

Case cited

S v Smith 2012(1) SACR 567 (SCA) [2011] ZASCA 15

Case cited

Guard Risk Insurance Co. Ltd v Kentz (Pty) Ltd (94/2013) [2013] ZASC 182; [2014] IALLSA 307 (SCA) (29 November 2013)

Case cited

Minister of Transport and Public Works, Western Cape & Another v Zanbuild Construction (Pty) Ltd & another 2011(5) SA 528 (SCA)

Case cited

Superior Courts Act 10 of 2013

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.