Secure Electronics v City of Cape Town (24107/2012) [2017] ZAWCHC 95 (13 September 2017)
The court held that the plaintiff's cause of action for the delay claim only arose upon completion of the contractual mechanism set out in clause 48 of the GCC, specifically when the engineer either approved the claim and issued a payment certificate or repudiated the claim. The issuing of a payment certificate was a condition precedent to payment, and until the claim was assessed and determined, no enforceable claim existed. The engineer repudiated the claim on 25 November 2011, and the summons was served on 7 January 2013, well within the three-year prescription period. The court rejected the defendant's argument that the plaintiff unilaterally delayed the running of prescription,...
- Citation
- [2017] ZAWCHC 95
- Parties
- Plaintiff: Secure Electronics; Defendant: City of Cape Town
- Court
- Western Cape High Court, Cape Town
- Jurisdiction
- South Africa
- Judgment Date
- 13 September 2017
- Case Number
- 24107/2012
- Procedural Posture
- Civil Procedure / Special Plea of Prescription Determined Prior to Main Hearing.
- Outcome
- Defendant's special plea of prescription dismissed; costs reserved for later determination.
- Judges
- Kusevitsky AJ
- Legal Topics
- Prescription Act, Construction Contracts, Delay Claims, Condition Precedent, Payment Certificates
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Secure Electronics
Plaintiff
City of Cape Town
Defendant
Procedural Posture
Civil Procedure / Special Plea of Prescription Determined Prior to Main Hearing.
Legal Issues
- 1 Whether the plaintiff's claim for compensation under the contract was extinguished by prescription.
- 2 When did the plaintiff's cause of action arise for purposes of prescription under the Prescription Act.
- 3 Whether the issuing of a payment certificate under the contract was a condition precedent to the plaintiff's entitlement to payment.
Ratio Decidendi
The court held that the plaintiff's cause of action for the delay claim only arose upon completion of the contractual mechanism set out in clause 48 of the GCC, specifically when the engineer either approved the claim and issued a payment certificate or repudiated the claim. The issuing of a payment certificate was a condition precedent to payment, and until the claim was assessed and determined, no enforceable claim existed. The engineer repudiated the claim on 25 November 2011, and the summons was served on 7 January 2013, well within the three-year prescription period. The court rejected the defendant's argument that the plaintiff unilaterally delayed the running of prescription,...
Court Disposition
Defendant's special plea of prescription dismissed; costs reserved for later determination.
Orders
- The Defendant's special plea of prescription is dismissed.
- Costs to stand over for later determination.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment