African Exploration Mining and Finance Corporation (SOC) Limited v LME Plant Hire (Pty) Ltd (060853/2023)
African Exploration Mining and Finance Corporation (SOC) Limited v LME Plant Hire (Pty) Ltd (060853/2023) [2024] ZAGPPHC 905 (9 September 2024)
The Court found that the applicant's delay in bringing the self-review application was unreasonable and inadequately explained, as the applicant failed to provide any substantive justification for not acting sooner. Nevertheless, the Court exercised its discretion to overlook the delay, given the public interest in preventing harm to the public purse and the fact that the rental agreement was concluded for an amount higher than the Board-approved contract price. The Court determined that the rental agreement was invalid due to lack of proper Board approval and breach of procurement conditions…
Source excerpt
- Self Review
- Delay In Legality Review
- Public Procurement
- Just And Equitable Relief
- Contractual Invalidity