Save the Maize Belt Society v Regional Mining Development And Environment Committe and Others (2014/15881) [2015] ZAGPJHC 254 (26 March 2015)
Court
South Gauteng High Court, Johannesburg
Case number
2014/15881
The court found that no recommendation was made by the Mining Committee on 16 April 2014 that could have prejudicial consequences for the applicant. The applicant failed to demonstrate that any substantive or procedural irregularity resulted in an adverse decision. The challenge to the applicant's legal status was dismissed as lacking merit. The record did not support grounds for recusal of the chairperson, nor did it show bias or procedural unfairness. The application was not frivolous or vexatious, and the ordinary rule regarding costs in constitutional litigation applied. The application f…
Pilanesberg Platinum Mines (Pty) Ltd v Chief Director: Mineral Regulations, Department of Mineral Resources and Others (61752/2013) [2014] ZAGPPHC 590 (29 July 2014)
Court
North Gauteng High Court, Pretoria
Case number
61752/2013
Judge
Molefe
The court found that the First Respondent acted ultra vires by imposing conditions requiring financial provision for rehabilitation based on the original EMP after approving amendments to the closure objectives. The conditions were not rationally connected to the information before the First Respondent, nor to the reasons given, and failed to consider relevant expert evidence supporting the feasibility of the amended closure objectives. The First Respondent's reliance on a worst-case scenario was unsupported and unreasonable. The statutory framework requires financial provision to be made in…
Mtunzini Conservancy v Tronox KZN Sands (Pty) Ltd and Another (10629/2012) [2013] ZAKZDHC 1; 2013 (4) BCLR 467 (KZD); [2013] 2 All SA 69 (KZD) (8 January 2013)
Court
Kwazulu-Natal High Court, Durban
Case number
10629/2012
Judge
Vahed
The Court held that when the first respondent commenced mining activities in 2002, only authorisation under the Minerals Act was required, and provincial planning approval under the Town Planning Ordinance was not necessary. The Minerals Act provided a comprehensive regulatory framework for mining, including environmental and land use controls, and provincial ordinances could not override national mining legislation. The 2008 amendment to the Town Planning Ordinance and the subsequent KwaZulu-Natal Planning and Development Act introduced planning approval requirements for mining, but these we…
ans Cuici Agri (Edms) Beperk and Another v Saamwerk Soutwerke (Edms) Beperk (540/07) [2007] ZANCHC 62 (16 November 2007)
Court
Northern Cape High Court, Kimberley
Case number
540/07
Judge
C C Williams
The court set aside an order granting a mining right after finding affected parties were not joined and material facts were withheld from the original application.
Maccsand CC v Macassar Land Claims Committee and Another (LCC 37/03) [2007] ZALCC 19 (14 August 2007)
Court
Land Claims Court
Case number
LCC 37/03
Judges
Gildenhuys, Pienaar
The Court held that the Commission on the Restitution of Land Rights qualifies as 'the State' for purposes of intervention under section 29(2) of the Restitution Act, given its public function in land reform. The Land Claims Court has jurisdiction to vary the Supreme Court of Appeal's order, as the original order specifically provided for such variation upon completion of mining and rehabilitation of Strips B and C. The legal dispensation for mineral rights has changed since the original order, with mineral rights now vested in the State and divorced from land ownership. The requirements for…
Maccsand CC v Macassar Land Claims Committee and Others (594/2003) [2004] ZASCA 114; [2005] 2 All SA 469 (SCA) (30 November 2004)
Court
Supreme Court of Appeal
Case number
594/2003
Judges
Farlam, Cameron, Mthiyane, Jafta, Patel
The Supreme Court of Appeal held that the interim interdict granted by the Land Claims Court was appealable because it had immediate and final effect on Maccsand's mining rights, which could be lost due to delays in the restitution claim. The requirements for an interim interdict were not fully satisfied, particularly regarding the balance of convenience, as the financial prejudice to Maccsand was severe and the prospects of the restitution claim being resolved soon were uncertain. The costs order at the interlocutory stage was inappropriate and should have been reserved. The contempt finding…