Seepe v Thermadyne Plant Rental and Another (J1013/2011)
Seepe v Thermadyne Plant Rental and Another (J1013/2011) [2016] ZALCJHB 186 (5 April 2016)
The Labour Court held that it is not competent to join a party to proceedings after a final order has been handed down, particularly where the party was not cited in the original referral to the CCMA. The applicant failed to comply with section 191 of the Labour Relations Act, which requires referral of a dispute to conciliation before adjudication. The authorities confirm that joinder is only permissible before judgment, and joining a party post-judgment would prejudice its rights without a hearing. The application for joinder was therefore dismissed.