Mmamoleboge Investments CC and Other v Crimson Properties 351 (Pty) Ltd and Others (23731/2018)
Mmamoleboge Investments CC and Other v Crimson Properties 351 (Pty) Ltd and Others (23731/2018) [2024] ZAGPPHC 303 (4 April 2024)
The court found that the Plaintiffs were appointed as subcontractors under the JBCC agreement and were instructed by the Department to remain on site during a nine-month cessation for reasons beyond their control. The Plaintiffs submitted claims for standing time and contract adjustment, which were approved and paid by the Department to the First Defendant. The First Defendant failed to pay the Plaintiffs the amounts due and did not provide credible evidence to support its defences of poor workmanship, prescription, or full and final settlement. The court rejected the First Defendant's argume…
Source excerpt
- Construction Contracts
- Standing Time Claims
- Contractual Adjustment
- Prescription
- Interest On Debt