Holding and result

The applicant disclosed a triable issue regarding the contractual obligation for installation of equipment, establishing a prima facie defence and warranting leave to defend the summary suit.

Court disposition

Application granted

Orders

  • Applicant granted leave to defend Commercial Case No.121 of 2022
  • Applicant to file written statement of defence within 21 days from date of ruling
  • Costs to be in the main cause

02

Material facts

Parties

Kahama Oil Mills Limited

Applicant Counsel: Ms. Janeth Njombe

Banca Monte Dei Paschi Di Siena S.P.A.

Respondent Counsel: Ms. Miriam Bachuba

Amounts and remedies

  • Contract Value: EUR 4,200,000
  • Initial Payment (15%): EUR 630,000

03

Procedural history

  1. Posture

    Miscellaneous Commercial Application / Ruling on Application for Leave to Defend Summary Suit

04

Questions and positions

Legal issues

Whether the applicant has disclosed a triable issue to warrant leave to defend the summary suit

Party arguments

Applicant
The applicant argued that there is a factual dispute regarding whether installation of equipment was part of the contractual consideration, and that a good defence exists against the summary suit.
Respondent
The respondent argued that the applicant has not demonstrated any triable issue as required by law.

05

Court’s reasoning

  1. 01

    Order XXXV Rule 3(1) of the Civil Procedure Code, Cap.33 R.E 2019

    Leave to defend a summary suit should be granted if the applicant discloses facts showing a triable issue or prima facie defence.

  2. 02

    Makungu Investment Co. Ltd vs. Petrosol (T) Ltd, Civil Appeal No.23 of 2013 (CAT)

    The court's role is to determine if there is a factual dispute to resolve and if the applicant has a good defence.

06

Ratio, limits and disposition

Ratio decidendi

The applicant disclosed a triable issue regarding the contractual obligation for installation of equipment, establishing a prima facie defence and warranting leave to defend the summary suit.

Obiter and limits

  • Whether installation was part of the consideration is a factual dispute requiring full hearing.

Court disposition

Application granted

  • Applicant granted leave to defend Commercial Case No.121 of 2022
  • Applicant to file written statement of defence within 21 days from date of ruling
  • Costs to be in the main cause

Source and reliance status

TANZLII · 1 January 2023

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

TANZLII

Judgment· 1 January 2023

MISC

IN THE HIGH COURT OF THE UNITED REPUBLIC OF

TANZANIA (COMMERCIAL DIVISION) AT DAR-ES-SALAAM MISC.COMMERCIAL APPLICATION NO. 31 OF 2023 KAHAMA OIL MILLS LIMITED ............................APPLICANT

VERSUS BANCA MONTE DEI PASCHI DI SIENA S.P.A....RESPONDENT

RULING Last Order: 09/05/2023 Date of Ruling 23/06/ 2023 NANGELA, J.: By way of a chamber summons made under Order XXV rule 3 (1) (a) and (b) and Order XLII Rule 2 of the Civil Procedure Code, Cap.33 R.E 2019 The Applicant herein has approached the Court seeking for the following orders, that: 1. Leave be granted to the Applicant to defend the suit (Commercial Case No.121 of 2022) filed by the Respondent by way of “Summary Procedure”, on 8th November 2022.

2. Costs of the Application be in the cause. Page 1 of 6 3. Any other order(s) or relief(s) as the Honourable Court shall deem fit and just to grant. The brief facts of this application are that some time in February 2018, the Applicant inked a contract for purchase and installation of bottling lines and blending section of spirits production with Ave Technologies S.L.R- Spinea (VE), a supplier. Under the contract, it was agreed that the Applicant would pay a total of Euro (€) 4,200,000 for the supply and installation of the two bottling lines and a blending section for spirits production, Glass Line suitable for filling spirits into 200ml glass bottles at a production speed of 12000bph. On the other hand, the Applicant was to pay 15% of the total consideration (i.e., Euro 630,000) to allow the supplier to perform her part of the consideration under the contract, same being the delivery and installation of the respective lines and blending section as agreed. The Applicant did comply and fulfilled her part, and the equipment were delivered for installations. As part of finalizing the remaining 85% payments obligation, the Applicant issued promissory notes in favour Page 2 of 6 of the supplier who later transferred them to the Respondent sometime in May 2019. The Respondent as a lawful holder in due course presented them to KCB Bank (T) Ltd but they were not fully honoured,

hence, the filing of Commercial Case No.121 of 2022 which the Applicant seeks leave to defend given that the case was filed under Order XXV- “SUMMARY PROCEDURE”. On the 10th day of May 2023, the parties appeared in Court for the hearing of this application. On the material date, Ms. Janeth Njombe, learned advocate appeared for the Applicant while Ms. Miriam Bachuba, learned advocate too, appeared for the Respondent. Ms. Njombe adopted the contents of the Applicant’s affidavit and the affidavit in reply to the counter affidavit and made a very brief submission urging this Court to grant the prayers sought by the Applicant. Relying on the case of Makungu Investment Co. Ltd vs. Petrosol (T) Ltd, Civil Appeal No.23 of 2013 (CAT) (unreported), she submitted, that, the role of a Court in an application like the one before this Court, is to decide whether or not there is a factual dispute to resolve and the Page 3 of 6 Applicant must only show that she has a good defence against the summary suit. Ms Njombe submitted that, the facts disclosed in the Applicant’s affidavit do sufficiently meet that requirement. Ms Njombe contended that, as per paragraphs 5, 10 and 11 of the supporting affidavit, the Applicant paid 15% of the total consideration agreed between the parties. However, the problem that emerged later was that, despite the contract being clear, the installation works were

not performed to date and, the Applicant has raised concerns arguing that the contract did as well cover for not only supply but also installation. In view of the above, she argued that there is a triable dispute between the parties and granting the orders sought is necessary. On the other hand, Ms. Bachuba has counteracted such a submission made by Ms. Njombe. Relying on the case of FB General Contractors and Another vs. Bank of Baroda Tanzania Ltd, Misc. Commercial Case No.18 of 2019, she argued that the Applicant has not demonstrated any triable issue as required by the law. Page 4 of 6 The issue which I need to consider is whether the Applicant has met the requirements of the law to warrant this Court to grant the prayers sought. Essentially, the two cases cited here above do share a common thing, that is, the Applicant must have a triable issue and must demonstrate facts which shows a prima facie defence. Order XXXV Rule 3(1) of the CPC. Cap.33 R.E 2019 provides, and I quote: “3-(1) The Court shall, upon an application by the Defendant, give leave to appear and to defend the suit, upon affidavit which:- (a) Disclose such facts as would make it incumbent on the holder to prove consideration, where the suit is on a bill of exchange or promissory note; (b) Disclose such facts as the Court may deem sufficient to support the application…” In this application before me, having

gone through the rival submissions made by the parties and looked at the affidavits filed by the Applicant, I do not hesitate to hold that, the same have disclosed that, there is a triable issue which necessitates the granting of the orders sought. Essentially, whether the issue of installation of the Page 5 of 6 equipment was part and parcel of the consideration as per the agreement between the parties, is a question or a factual dispute that requires attention. I am contented, therefore, that, there is a prima facie defence which would warrant a full hearing of both parties, a fact which warrant that the Applicant be granted this application. In the upshot of the above conclusion, this Court settles for the following Orders: (a) That, this application is hereby granted. (b) The Applicant is to file her written statement of defence to the Commercial Case No.121 of 2022 within 21 days from the date of this ruling. (c) Costs shall be in the main cause. It is so ordered. DATED AT DAR-ES-SALAAM ON THIS 23rd DAY OF JUNE 2023 ...................................

DEO JOHN NANGELA

JUDGE Page 6 of 6

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Makungu Investment Co. Ltd vs. Petrosol (T) Ltd, Civil Appeal No.23 of 2013 (CAT)

Case cited

FB General Contractors and Another vs. Bank of Baroda Tanzania Ltd, Misc. Commercial Case No.18 of 2019

Case cited

Civil Procedure Code, Cap.33 R.E 2019

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.