The application was dismissed because the applicants introduced new facts beyond those for which leave was granted, violating mandatory procedural rules. The evidence established that the 3rd Respondent became aware of the fraud on 30/03/2023, making the complaint timely. No denial of fair hearing or misallocation...

Source-derived case information.

Citation
M
Parties
Applicant: M/S Dezo Civil Contractors Company Ltd; Applicant: M/S Harasini Enterprises Ltd; Respondent: Public Procurement Appeals Authority; Respondent: Public Procurement Regulatory Authority; Respondent: Ocean Road Cancer Institute; Respondent: Attorney General of the United Republic of Tanzania
Court
TANZLII
Jurisdiction
Tanzania
Judgment Date
14 September 2023
Procedural Posture
Judicial Review (miscellaneous Cause) / Ruling on Preliminary Objections and Main Application
Outcome
Application dismissed
Legal Topics
Judicial Review, Certiorari, Mandamus, Procedural Compliance, Right to Fair Hearing, Burden of Proof, Public Procurement Appeals, Debarment
Source Language
en
Administrative Law Public Procurement Law Judicial Review Certiorari Mandamus Procedural Compliance Right to Fair Hearing Burden of Proof +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 20 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

M/S Dezo Civil Contractors Company Ltd

Applicant

M/S Harasini Enterprises Ltd

Applicant

Public Procurement Appeals Authority

Respondent

Public Procurement Regulatory Authority

Respondent

Ocean Road Cancer Institute

Respondent

Attorney General of the United Republic of Tanzania

Respondent

Procedural Posture

Judicial Review (miscellaneous Cause) / Ruling on Preliminary Objections and Main Application

  1. 1 Whether the application for judicial review was fatally defective for non-compliance with prescribed forms and inclusion of new facts beyond those for which leave was granted
  2. 2 Whether the applicants were denied a fair hearing due to late or incomplete service of documents
  3. 3 Whether the complaint to the Public Procurement Regulatory Authority was lodged out of time

Ratio Decidendi

The application was dismissed because the applicants introduced new facts beyond those for which leave was granted, violating mandatory procedural rules. The evidence established that the 3rd Respondent became aware of the fraud on 30/03/2023, making the complaint timely. No denial of fair hearing or misallocation of burden of proof was found. The debarment penalty was properly imposed jointly due to the nature of the joint venture and power of attorney arrangement.

Court Disposition

Application dismissed

Orders

  • Application for prerogative orders of certiorari and mandamus dismissed
  • No order as to costs