20051026 TZHC Dar es Salaam

20051026 TZHC Dar es Salaam

The court adopted the deed of settlement as the judgment and decree, as both parties agreed to settle the matter out of court.

Source-derived case information.

Citation
20051026 TZHC Dar es Salaam
Parties
Appellant: Siemens Tanzania Ltd; Respondent: Jumannee Kadaso
Court
TZHC
Jurisdiction
Tanzania
Judgment Date
26 October 2005
Procedural Posture
Civil Appeal / Settlement Before Hearing of Appeal
Outcome
settled by consent; deed of settlement adopted as judgment and decree
Legal Topics
Negligence, Workman Compensation, Damages, Settlement
Source Language
en
Tort Law Employment Law Negligence Workman Compensation Damages Settlement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Siemens Tanzania Ltd

Appellant

Jumannee Kadaso

Respondent

Procedural Posture

Civil Appeal / Settlement Before Hearing of Appeal

  1. 1 Whether the appellant was liable for damages arising from negligence after workman compensation had been paid
  2. 2 Whether the parties could settle the matter out of court and have the settlement adopted as a court decree

Ratio Decidendi

The court adopted the deed of settlement as the judgment and decree, as both parties agreed to settle the matter out of court.

Court Disposition

settled by consent; deed of settlement adopted as judgment and decree

Orders

  • Defendant to pay plaintiff Tshs 7,000,000 as full and final settlement within 14 days
  • Each party to bear own costs