Horodyski v. I.C. Property Management Solutions Inc.
The defendant breached the contract by failing to properly prepare the bitumen surface and by using improper materials, causing delamination; the claim was discoverable only when the defendant ceased warranted repairs and communication in late October 2023, so the action was timely; damages are measured by replacement cost adjusted for betterment but limited to the Small Claims Court monetary jurisdiction, resulting in a judgment for the claimant.
Source excerpt
- Breach of contract
- Workmanship warranty
- Limitations period - discoverability
- Damages - expectancy and betterment
- Expert evidence admissibility