CHC Construction Ltd. v. He
The plaintiff breached the contract by wrongfully demanding payments outside the agreed progress payment schedule, refusing to complete the work unless paid, failing to perform the work in a good and workmanlike manner, and failing to complete within the 30 business days; the defendant did not breach and is entitled to damages to place him in the position had the contract been performed; damages awarded $9,384.37, plaintiff's claim dismissed, defendant's counterclaim allowed, builder's lien cancelled and costs to defendant.
Source excerpt
- Breach of contract
- Repudiation
- Progress payments
- Workmanship
- Extras
- Damages