Parhar v. West Point Pacific Construction (64th Ave) Ltd.
The Assignment Agreement contained material inconsistencies and ambiguities among clauses 5.2, 5.4 and 5.8 regarding payment amounts, payees and trust handling; the plaintiffs failed to adduce necessary evidence of surrounding circumstances to permit the court to find the facts required for a final determination. Consequently the defendants were not bound to lose and the court must dismiss both the R.9-6 summary judgment application and the R.9-7 summary trial application, while leaving the parties free to re-apply if they can adduce further evidence to establish the surrounding circumstances.
Source excerpt
- Contract interpretation
- Deposit
- Assignment of contract
- Summary judgment
- Summary trial
- Surrounding circumstances