Sign in
Canada Source-linked decisions Coverage checked

Canada Case Law

Search judgments by proposition, citation, court, judge or legal topic, then move directly into the source-grounded case analysis.

Courts on this page
4 court collections
Last checked

Canada decisions

Decisions matching the current search

Clear filters
Contract law 2026 BCSC 699

Clarity Architectural Products Inc. v. Gryphon Corporate Construction Ltd.

The defendant's conduct (direction to pause, non-payment of the Second Invoice, failure to return shop drawings, and engaging a replacement subcontractor while leaving the subcontractor under the impression work would continue) objectively amounted to repudiation of the Subcontract; the plaintiff validly accepted that repudiation by June 12, 2024; therefore the plaintiff is entitled to expectation damages rather than the limited recovery available under a prospective termination for convenience. Damages awarded consist of the unpaid Second Invoice ($664,071.46) recoverable as a debt and under…

  • Repudiation
  • Termination for convenience
  • Expectation damages
  • Interest
  • Honest performance/good faith
  • Mediation default
Read case analysis
Contract law 2026 BCSC 686

Blankstein v. Hayes Davis Investments Inc.

Summary judgment dismissed because material triable issues exist: evidence supports that the Option Agreement may be intimately connected to the services agreement (Sail Labrador) and factual disputes remain about whether defendant's conduct hindered exercise or justified equitable relief to excuse non-compliance; these issues cannot be resolved on a Rule 9-6 application.

  • Option agreements
  • Specific performance
  • Failure of consideration
  • Summary judgment
  • Relief from forfeiture
  • Substantial non-performance
Read case analysis
Contract law 2026 BCCA 143

Northern Health Authority v. du Plessis

The Court dismissed both the appeal and cross‑appeal because the central questions identified by the parties were predominantly mixed questions of fact and law arising from the arbitrator's factual findings and application of legal tests; the arbitrator reasonably concluded the PHO Order did not apply to the respondent given his unique factual arrangement and did not err in law in his interpretation; the cross‑appellant failed to identify an extricable question of law arising from the remedy award.

  • Frustration of contract
  • Statutory interpretation
  • Termination without cause
  • Reasonable notice
  • Repudiation
  • Damages
Read case analysis
Contract law 2026 BCSC 582

CHC Construction Ltd. v. He

The plaintiff breached the contract by wrongfully demanding payments outside the agreed progress payment schedule, refusing to complete the work unless paid, failing to perform the work in a good and workmanlike manner, and failing to complete within the 30 business days; the defendant did not breach and is entitled to damages to place him in the position had the contract been performed; damages awarded $9,384.37, plaintiff's claim dismissed, defendant's counterclaim allowed, builder's lien cancelled and costs to defendant.

  • Breach of contract
  • Repudiation
  • Progress payments
  • Workmanship
  • Extras
  • Damages
Read case analysis
Construction law 2026 BCSC 401

Chung v. Klein Homes Ltd. 0717233

The appeal is dismissed because the trial judge did not commit palpable or overriding errors: he acted within the broad discretion afforded by the Small Claims Act and Rules in admitting and weighing disclosure, permissibly allowed a mid-trial correction to the counterclaim, correctly interpreted the contract and Builder's Lien provisions to treat payment as due on occupancy/substantial completion, and correctly concluded the appellants repudiated the contract by occupying without paying final sums, leaving the trial judgment and resultant set-off intact.

  • Repudiation
  • Substantial completion
  • Interim occupancy
  • Late disclosure
  • Amendment of pleadings
  • Damages
Read case analysis
Employment law 2026 BCSC 713

McGill v. Berry and Smith Trucking Ltd.

The court granted summary trial, upheld the without-cause termination clause, found no repudiation from late final-wage payment or alleged bullying, and dismissed the action.

  • Wrongful dismissal
  • Repudiation
  • Termination clause enforcement
  • Esa s.18 - timing of final wages
  • Workplace bullying
  • Aggravated damages
Read case analysis
Contract law 2026 BCSC 334

Smithe Residences Ltd., by its receiver, MNP Ltd. v. Boffo Investment Corp.

The court held the Smithe Consulting Agreement replaced the JVA, its profit‑sharing waterfall applied to profits from the whole completed Smithe Project (not limited to the plaintiff's proposed Thalia design), the plaintiff did not repudiate the agreement, Boffo Smithe breached by withholding profit shares, and Boffo Investment was unjustly enriched by receipt of those profits; damages awarded under the contract waterfall and unjust enrichment principles.

  • Contractual interpretation
  • Repudiation
  • Good faith in contractual performance
  • Profit‑sharing
  • Joint venture agreements
  • Remedies and damages
Read case analysis
Contract 2026 BCCA 103

Anderson v. Double M Construction Ltd.

The stay application was dismissed because the appellant failed to meet the low merits threshold and the balance of convenience favoured the respondents; however, a limited temporary stay of the vacant possession order until March 31, 2026 was granted to mitigate relocation hardship.

  • Repudiation
  • Forfeiture of interest
  • Vacant possession
  • Summary trial (rule 9-7)
  • Stay of execution
  • Security for costs
Read case analysis
Contract law 2026 NSCA 13

FH Development Group Inc. v. Brooks

Because the Brooks did not accept FH's anticipatory breach, the duty to mitigate did not arise until the actual breach on the closing date; the trial judge's factual findings that FH's conduct destroyed trust and that the Brooks' purchase on the competitive open market was reasonable were supported by evidence and insulated the damages award from reversal.

  • Anticipatory breach
  • Mitigation of damages
  • Reasonable mitigation
  • Repudiation
  • Purchase of replacement property
Read case analysis
Contract law 2025 NSSM 77

Veinot v Creaser

The defendant repudiated the contract by abandoning the project and ceasing communication for an extended period; the claimant was entitled to treat the contract as terminated and recover restitution of unearned payments plus the proven overage and modest general damages and filing costs; the counterclaim was dismissed.

  • Repudiation
  • Breach of contract
  • Assessment of damages
  • Restitution of advance payments
  • Mitigation
  • Dismissal of counterclaim
Read case analysis

About this LexChat collection

Canada decisions are organised by court, judge, legal area and indexed issue so a practitioner can move from a proposition to a citable authority with the surrounding context intact.