Sroda Construction Ltd, R (On the Application Of) v Elmbridge Borough Council
Sroda Construction Ltd, R (On the Application Of) v Elmbridge Borough Council [2026] EWHC 967 (Admin) (24 April 2026)
Permission for judicial review was refused as out of time. The court also held that, even if timely, challenges over solar panels and notice would have failed.
- Judicial-review-time-limits
- Material-planning-considerations
- Notification-requirements-in-planning
- Renewable-energy-as-planning-consideration
- Judicial-review
- Planning-law