4 Jan 2024
CHAN CHEUK KIT v. SMARTA INNOVATION TECHNOLOGY CO LTD AND ANOTHER
- Citation
- [2024] HKDC 49
- Court
- District Court
- Case number
- DCCJ3564/2021
Clause 5 was properly engaged because on the balance of probabilities the Company had substantial outstanding liabilities on the Completion Date in breach of clause 8; that breach justified Plaintiff withholding completion and treating the HK$1.5M as a loan under clause 5 with contractual interest; accordingly judgment entered for Plaintiff against D1 and D2 (as guarantor) for principal and contractual interest; 2nd Defendant's defences and counterclaim failed for lack of evidence.